Date:
Participants
Shankaranarayanan Puzhavakath Narayanan
Agenda
Status of various components – implementation
- Overview of progress
- Updates to Jiras
- Any open points
- Update assumptions and any short-cuts in wiki
- NFR status
- Modeling updates
- Option 2 csars available
- Option 1 - SDC availability
- Endpoints conclusion
- Michela's mail reg. follow-on actions
- Test setup
- MVP test cases to be drafted
- See proposal below in Notes section for environment
- Check feasibility and availability in DT Lab, else request for a tenant in Windriver
- Oct 1-8 is holiday in China
- Use case documentation
- Honolulu requirements
- Start with improvements/enhancements to Guilin functionality
- Any additional inputs?
Notes and Actions
Track | Proposed Test lab | Dependency |
---|---|---|
Frankfurt enhancements | CMCC | |
RAN Slicing (Option 1) | Winlab | Requires also Transport NSSMF functionality to be available |
RAN Slicing (Option 2) | CMCC | Requires also Transport NSSMF functionality to be available, requires external RAN NSSMF and RAN-Sim to be available |
Core Slicing (Option 1) | TBD | Requires Core NF simulator to be available |
Core Slicing (Option 2) | CMCC | Requires external Core NSSMF |
Transport Slicing (both options) | TBD | |
KPI Monitoring | CMCC | Requires DL, DFC and PM Mapper functionality to be stable |
Closed Loop | Winlab | Requires RAN Slicing (Option 1) to be stable, PM Mapper functionality to be available |
Intelligent Slicing | Winlab | Requires RAN Slicing (Option 1) to be stable, PM Mapper functionality and RAN-Sim to be available |
E2E for Option 1 | Winlab | Requires RAN, Core and Transport Slicing for Option 1 to be stable |
E2E for Option 2 | CMCC | Requires RAN, Core and Transport Slicing for Option 2 to be stable |
Recording