Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
ONAP supporting multiple onboarding formats | work with VNF SDK, VVP and SDC to minimize the risk. | Document the desired direction in the forward looking VNF Guidelines |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
...
Date | Project | Deliverable |
---|---|---|
1/16/18 | Sprint 1 7 start | Draft M1 Project Plan available on VNFRQTS Project Wiki M1 checklisy available before ONAP Beijing M1 Milestone - planning process complete 1/18 |
1/30/18 | Sprint 1 7 complete Sprint 2 8 start | Draft structure of Use case and test case Descriptions available before ONAP Beijing M2 Milestone - functionality freeze 2/12 |
2/13/18 | Sprint 2 8 complete Sprint 3 9 start | |
2/27/18 | Sprint 3 9 complete Sprint 4 10 start | before ONAP Beijing M3 Milestone - API data model freeze 3/8 |
3/13/18 | Sprint 4 10 complete Sprint 5 11 start | |
3/27/18 | Sprint 5 11 complete Sprint 6 12 start | before ONAP Beijing M4 Milestone - code freeze 3/29 |
4/10/18 | Sprint 6 12 complete Sprint 7 13 start | Finalize complete drafts before ONAP Beijing RC0 Milestone 4/19 |
4/24/18 | Sprint 7 13 complete Sprint 8 14 start | Bug fixes only prior to RC1 5/3 |
5/8/18 | Sprint 8 14 complete Sprint 9 15 start | Bug fixes only prior to RC2 5/17 |
5/22/18 | Sprint 9 15 complete | Bug fixes only prior to signoff 5/24 |
...