BBS - DevelopmentPlan


TaskLeadStartEndStatus
1Requirement Analysis



1.1Finalize BBS architecture
Mon 11.26.18Tue 12.11.18

COMPLETED

1.2Building Team
Mon 11.26.18Wed 12.05.18

COMPLETED

1.3Create Epics In Community JIRA
Tue 12.11.18Fri 12.21.18

COMPLETED

1.4Create user stories In Community JIRA
Fri 12.21.18Tue 12.25.18

COMPLETED

1.5Make Workloads, Acceptance criteria, Plan, Dependencies
Tue 12.25.18Mon 1.07.19

COMPLETED

1.6

Low Level Design (Output specification for project design to review)

1. LLD for SDN-C & Access SDN M&C
2. LLD for SDN-C & Edge SDN M&C
3. LLD for VES Event definition
4. LLD for topology discovery from SDN M&C
5. LLD for External API
6. LLD for PRH enhancement


Mon 1.07.19Mon 1.14.19

IN PROGRESS

1.7Low Level Design review
Mon 1.14.19Thu 1.17.19


1.8Model freeze
Mon 11.26.18Tue 12.11.18

COMPLETED

1.9Model review
Tue 12.11.18Tue 12.18.18

COMPLETED

1.10Model pushed to the community
Thu 1.24.19Tue 2.05.19


1.11API freeze
Tue 12.18.18Tue 12.25.18


1.12API review
Tue 12.18.18Tue 12.25.18


1.13API pushed to he community
Thu 1.24.19Mon 3.04.19


2Coding



2.1Code freeze
Tue 12.25.18Fri 2.08.19


2.2Weekly Code review
Tue 12.25.18Fri 2.08.19


2.3Unit test
Tue 12.25.18Fri 2.08.19


2.4Code pushed to the community
Tue 12.25.18Thu 3.28.19


3Testing



3.1E2E Test design and demo strategy
Mon 1.07.19Wed 1.16.19

IN PROGRESS

3.2E2E Test design and demo strategy review
Wed 1.16.19Fri 1.18.19


3.3Internal Demo review
Mon 1.07.19Tue 1.15.19


3.4Develop test plan
Fri 2.08.19Tue 2.12.19

IN PROGRESS

3.5Project Test case output
Fri 2.08.19Tue 2.12.19


3.6Project Interface self test
Fri 2.08.19Wed 2.27.19


3.7Integration test plan
Fri 1.18.19Fri 1.25.19

IN PROGRESS

3.8Integration Test case output
Fri 1.25.19Sat 1.26.19


3.9Integration test
Fri 2.08.19Sat 3.09.19


3.10Internal Demo Show Round1
Mon 3.11.19Wed 3.13.19


3.11Internal Demo Show Round2
Mon 3.18.19Wed 3.20.19


4Lab Setup



4.1Development Environment (CI/CD, Code repo)
Mon 11.26.18Fri 12.07.18

IN PROGRESS

4.2Development Environment (local env, local test env)
Mon 11.26.18Fri 12.07.18

COMPLETED

4.3Detailed lab topology (wiring diagram)
Wed 12.26.18Wed 1.09.19

COMPLETED

4.4Detailed lab topology (wiring diagram) review
Wed 1.09.19Wed 1.09.19

COMPLETED

4.5Material ready
Wed 12.26.18Wed 1.09.19


4.6Demo Lab setup
Fri 2.01.19Mon 2.25.19

COMPLETED