Issues

Root Causes

Suggestions and discussion

-          The TSC agenda management and time management could improve to get the most out of the time.  We also need to move from reporting to discussions/decisions that assist the community.  Maybe split the into 3 parts (though maybe 2 parts depending on where we are in the release).  Time cap (can’t put all that on LF).

-          We don’t do decision follow-up very well.  We have made decisions with no follow-up. We could consider TSC level “Jiras” for topics or issues to address to help with the TSC project management.

-          For the common way to store minutes across the projects etc; maybe we need to have a best practice project/subcommittee that the rest can slowly adopt to.  And follow-up.

Agreed action plan

4/12/18 Recording: audio_only.m4a