Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre committed Product Backlog Stories been coded and marked as "Done" in Jira?No


Are all tasks associated with committed Product Backlog Stories been marked as "Done" in Jira?No


Provide the project features list under the form of a bulleted list.N/A

Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off

N/A

Release ManagementHave all issues pertaining to FOSS been addressed?Yes

Have all findings from previous milestones been addressed?YesProvide link to JIRA findings
DevelopmentAre all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

Are all binaries available in Nexus Release repository?Yes

https://nexus.onap.org/content/repositories/releases/org/onap/oparent

https://nexus.onap.org/content/repositories/releases/org/onap/demo


Are all Docker images available In Nexus?N/A

Are the Java and Docker manifest updated with the same version as in Nexus Release repository?Yes

Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?N/AProvide link to evidenceGoal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs
Has the project code successfully passed the Daily Build process?N/AProvide link to evidenceGoal is to ensure the latest project commit has not broken the Integration Daily Build 

Has the project done the integration testing with related dependent projects?

N/A

Documentation

Has your team contributed and completed work in the following documentations in ReadTheDocs:

  1. Release Notes
  2. Project Documentation

Yes

(no release notes)

Provide Link to ReadTheDocs Release Notes

Provide Link to ReadTheDocs Project Documentation