M2/M3

Charts

M2/M3 Feedback to Projects

77% of M2/M3 Activities are completed

APPC, CLAMP, MSB, Modeling, UUI, VNFREQS, VVP  have successfully passed M2/M3 milestone

yyy have partially passed M2/M3 milestone

AAI

  • Jan 20 - API Docs concurrence under discussion ()
  • Jan 20 - SDK 2.6 integration (debugging mode) - 
  • Jan 20 - Need to confirm "Continue with unencrypted use of Elasticsearch" as mitigated plan is acceptable from Legal/security perspectives
  • Jan 20 - wave 1 containers will be released by mid-week week of 1/19
  • Jan 20 - Require feedback from ZTE about  (High Defect on ESR)

AAF

  • Jan 20 - 1 Blocker - 

  • Jan 20 - AAF is part of wave1 so docker container is expected as part of M2/M3 milestone

  • Jan 20 - Need to confirm API docs, OOM ports list are completed and Architecture review was performed


CCSDK

  •  Jan 20 - High issues to be solved - need to identify if any are blockers for the Integration Team
  •  Jan 20 - Need to confirm API docs, Data Models are completed and Architecture review was performed

DCAEGEN

  • Jan 20 - Portal SDK Integration - Waiting for code to be submitted (DCAEGEN2-1921)

  • Jan 20 -  High issues to be solved - need to identify if any are blockers for the Integration Team

DMAAP

  •  Jan 21 - Need to confirm that there is no Risk for DMaaP

  •  Jan 21 - DMaaP is part of wave1 so docker container is expected as part of M2/M3 milestone

EXTAPI

  •  Jan 21 - OOM port to be updated (question)


INTEGRATION

  • Jan 21 - Review remaining gerrit submission

Multicloud

  • Jan 21 - OOM port to be updated (question)
  • Jan 21 - Review remaining gerrit submission
  • Jan 21 - 1 High issue - 
  • Jan 21 - Is there any risk associated to your project?

MUSIC

  • Jan 21 - Review remaining gerrit submission

OOM

  • Jan 21 - Review remaining gerrit submission

  • Jan 21 - Is there any risk associated to your project?
  • Jan 21 - Complete any preliminary docs?
  • Jan 21 - Need to confirm Architecture Review has been performed.
  • Jan 21 - High issues to be solved - need to identify if any are blockers for the Integration Team 

OOF 

  •  Jan 21 - Review remaining gerrit submission

Policy

  • Jan 21 - High issue to be solved 


Portal

  • Jan 21 - High issues to be solved - need to identify if any are blockers for the Integration Team 
  • Jan 21 - Is there any risk associated to your projec to be updatedt?
  • Jan 21 - AAF is part of wave1 so docker container is expected as part of M2/M3 milestone
  • Jan 21 - Review remaining gerrit submissions

SDC

  • Jan 21 - Review remaining gerrit submissions
  • Jan 21 - SDC is part of wave1 so docker container is expected as part of M2/M3 milestone
  • Jan 21 - OOM port to be updated (question)
  • Jan 21 - License issue to be solved
  • Jan 21- Need an update about Portal SDK Integration
  • Jan 21 - High issues to be solved - need to identify if any are blockers for the Integration Team  

SDNC

  •  Jan 21 - Need to confirm API docs are completed and Architecture Review was performed
  •  Jan 21 - OOM port to be updated (question)
  • Jan 21 - High to be solved - 

SO

  • Jan 21 -Architecture Review is scheduled on 1/21
  • Jan 21 - Review remaining gerrit submissions
  • Jan 21 - Highest/High issues to be solved - need to identify if any are blockers for the Integration Team 

VF-C

  •  Jan 21 - Review remaining gerrit submission


VID

  • Jan 21 - VID is part of wave1 so docker container is expected as part of M2/M3 milestone
  • Jan 21 - Is there any risk associated to your project?
  • Jan 21 - Portal SDK Integration (under testing)

VNFSDK

  •  Jan 21 - Review remaining gerrit submissions


M1

Charts

  

M1 Feedback to Projects (11/20)

M1 Projects Approved on 11/14  AAI, AAF, APPC, CLAMP, CCSDK, DCAE, DMaaP; ExtAPI, Integration,  Modeling, MUSIC, MSB, MutliCloud, OOM, Policy, SNDC, SDC, SO, VF-C, VID, VNFReqs, VVP, VNFSDK

M1 Projects Ready for approval: OOF, UUI, PORTAL

NO GO- CLI, HOLMES, LOGGING


==================================================================================

??? - impact on use case/requirement: OOF, PORTAL, UUI

Plan to move forward

Can we help the PTL with additional people? - PTL to confirm or not they have got additional feedback by 11/19 EOD

If not then can the impacted requirements/use cases be re-assessed?

                    if they can still deliver their use cases/requirements without them  - Owners to re-assess by 11/21 EOD

                   if not then shall we make an exception? TSC final vote

============================

NO GO- no impact on use cases/requirements: CLI, HOLMES, LOGGING

=> Re-use El Alto containers except if any blocking issue are identified during the Frankfurt testing cycle by the Integration Team.

      Any other finding (security, non blocking issue) should be documented in the Frankfurt Release Note

===========================

Major resource constraint for PORTAL, CLI - CALL For Help


AAF

  • Arch team to meet with AAF prior to M2 to review arch changes.

  • New API

Application Controller

  • Gating issue for code coverage goal  - Require IT Support: IT-17899

  • Arch team to meet with Application Controller team prior to M2 to review architectural changes.  See 

  • New API - see 

Clamp

  • Requires architectural review.  See 

  • Moving to Java 13.  See 

MULTICLOUD

  • Python 3 migration completed except for multicloud-azure.  See 

OOM

  • Architectural review required by M2.  See 

OOF

  • JBB Jenkins jobs to be fixed to support Python 3.0: OPTFRA-630

PORTAL

  • IBM team will help on this requirement. See 

  • Will keep open this ticket since the team will use it to track their integration with oParent

SDC

  • Raise an IT Ticket to remove SONAR jenkins job on SDC-jtsoca.


CLI - Not part of the release (TSC vote on 11/14)

  • No Resource to work on Vulnerability Table .  See 

HOLMES -Not part of the release (TSC vote on 11/14)

  • Need to complete the remaining Release Management tickets

LOGGING - Not part of the release (TSC vote on 11/14)