Release Schedule r5 (approved  )

Activity Log

DateEvent or UpdateMilestones Affected
Apr 29TSC approved Honolulu sign-offSign-Off
Apr 15TSC approved schedule (r5)RC1, RC2, Sign Off
Apr 8Proposal for RC1, RC2, Sign Off (r5) (Note: r4 proposed but not approved)RC1, RC2, Sign Off
Apr 2Proposal for RC1, RC2, Sign Off (r4)RC1, RC2, Sign Off
Apr 1Consensus with OOM and INT that RC0 requirements met (TSC e-mail vote in progress). Action to propose schedule for RC1, RC2, Sign OffRC0
Mar 29RC0/RC1 requirements not met.  Re-evaluate on April 1.RC0, RC1
Mar 25RC0/RC1 requirements not met.  Re-evaluate on Mar 29.RC0, RC1
Mar 18TSC approved plan to merge RC0 with RC1 on March 25RC0
Mar 11TSC approved schedule proposal (see Mar 10 below)RC0, RC1, RC2, Sign Off
Mar 10Blocking issue reported for RC0. Propose 1 w slip to RC0 → Sign Off (r2).  Sign off moves to April 8.RC0, RC1, RC2, Sign Off
Mar 1TSC approves M3 with exceptions.  Exceptions to be closed by RC0.M3
Feb 25TSC determined that there is insufficient information to make decision, so M3 pushed out 4 days to March 1M3
Feb 1Uploaded ONAP Honolulu r1 to show changes to M1 and M2 datesM1, M2
Jan 25M2 approved with exceptionsM2
Jan 21Requirements not met. M2 slipped to Jan 25M2
Jan 14M1 approved with exceptionsM1
Jan 11Requirements not met.  M1 slipped to Jan 14M1
Dec 10TSC approved scheduleALL
Dec 10M1 moved out 4 days to Jan 11M1
Nov 20Second draft posted
Nov 11First draft posted