- #AGREED the TSC approves the OOM Gitlab POC using CLA validation via the ci chain demonstrated in https://gitlab.com/kopasiak/oom_cla_test/-/merge_requests/1 as a workaround until EasyCLA supports GitLab
- #AGREED Istanbul M3 slips until Sept. 2nd; discussion with the PTLs on Monday to understand the status and their blockers
- #AGREED ESR UI/ESR Server is to be removed from ONAP beginning with Istanbul
#AGREED where the copyright statement names ONAP specifically remove the year.
i.e. for RTD copyright it would read:© Copyright ONAP. Licensed under Creative Commons Attribution
4.0
International License Revision 5862ac2c.
July
- #AGREED TSC approves that for Istanbul we maintain the current stability/resiliency acceptance criteria until community members raise an improvement request to be assessed for the next release.
- #AGREED since the TSC is approving unmaintained projects in a release the exception filing should be made by the TSC itself. (in reference to AAI-ESR)
- #AGREED the TSC approves that Due to the complexity of the OOM project, the ONAP TSC agrees that the OOM project (code & CI jobs) moves under Gitlab as soon as the CLA is approved. If CLA is not approved by Aug 19th then the ONAP TSC will reconvene to assess other options/alternatives to support the OOM project. Currently only the OOM project (all repos) is targeted to move to Giltab
June
- #AGREED extension on exceptions to M2 of one week, due to extended arch review schedule to June 29
- #AGREED on pursuing a POC for ScanCode.io - we need to identify where to run the POC.
- #AGREED: the TSC approves the SonarCloud profile management model as described in the Proposal
- #AGREED that the regular elections of the TSC shall occur annually in September
May
- #AGREED the TSC approves
andJira server ONAP Jira serverId 425b2b0a-557c-3c0c-b515-579789cceedb key REQ-396
as TSC best practices for JakartaJira server ONAP Jira serverId 425b2b0a-557c-3c0c-b515-579789cceedb key REQ-399 - #AGREED TSC moves the VID and ExtAPI projects to Unmaintained status.
...
- Istanbul schedule proposal - M1 on May 20th, 2021 - #AGREED TSC approved the Istanbul release (v.7 https://wiki.onap.org/x/DiSLBQ)
#AGREED We will start the "unmaintained State" process for the VID and EXTAPI projectsSuperseded by TSC 2021-05-27
April
...