AgendaMinutes (Draft to be updated during call)
Slides

High Priority Bugs


High priority defects :

 

Jira
serverONAP JIRA
jqlQueryproject = "Service Design and Creation" AND issuetype = Bug AND status not in (closed) AND priority in (High, Highest) ORDER BY priority DESC
serverId425b2b0a-557c-3c0c-b515-579789cceedb


Open review
Jakarta Release timeplan

 

M1 (Global requirement freeze) scheduled for 2nd December

Release Planning: Jakarta

 

Tasks for M1:

Jira
serverONAP Jira
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySDC-3786

 

M1 postponed by 1 week from 2nd to 9th Dec. Other milestones unaffected

We should plan to release more often in Jakarta to move towards a more CI way of working. 

 

M1 approved by TSC

 

M2 milestone scheduled for 27th January

 

First delivery for Jakarta (1.10.0) built and submitted to OOM (https://gerrit.onap.org/r/c/oom/+/126602). Content can be seen here: https://docs.onap.org/projects/onap-sdc/en/latest/release-notes.html#version-1-10-0

Still in review in OOM

1.10.1 built and submitted to OOM (https://gerrit.onap.org/r/c/oom/+/127003)

M2 passed last Thursday 3rd Feb. Next milestone is M3 on 3rd March

 

M3 planned for Thursday week 3rd March - last date for merging in functional changes for Jakarta.

Code Coverage currently at 55.6% - must maintain above 55%

 

1.10.1 merged in to OOM

M3 this Thursday 3rd Mar

 

M3 approved last Thursday. No new functionality can be added to Jakarta, only big fixes, documentation etc.

M4 planned for 24th March

 

1.10.2 images built, but bug fixes merged in since, will create new version including bug fixes for inclusion in OOM

 

M4 postponed to this Thursday 30th March, other milestones not affected

OOM review:

SDC: https://gerrit.onap.org/r/c/oom/+/128003

SDC-WFD: https://gerrit.onap.org/r/c/oom/+/127872

 

M4 approved by TSC last Thursday, RC planned for 28th April

OOM reviews continuing

 

OOM reviews for SDC and SDC-WFD merged.

RC planned for Thursday 


Kohn timeplan

 

Kohn timeplan has been approved by TSC.

M0 was last Thursday 7th Apr

 

M1 (Global requirement approved) planned for 26th May


Kohn Impacts

Jira
serverONAP Jira
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keySDC-3777
- Implementation started

Jira
serverONAP Jira
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyREQ-1044
- Implementation started

Any other proposals welcome


Portal ReplacementProposal from DT to replace existing portal (which is unmaintained) with new portal developed by DT
Bugs

Jira
serverONAP Jira
jqlQueryproject = SDC and type = Bug AND status not in (Closed, Delivered, Done, "Not a bug")
serverId425b2b0a-557c-3c0c-b515-579789cceedb


No meeting next week

No meeting 2nd May due to public holiday in Ireland, next meeting 9th May


...