RC Release Candidate Milestone overview is available in wiki.
Practice Area | Checkpoint | Yes/No | Evidences |
---|
How to?Comments |
---|
Product Management | Are all tasks associated with the release been marked as "Done" in Jira? | Yes | Link to tasks | Remaining Task is Delivered, waiting for originator to close |
| Have all findings from previous milestones been addressed? | Yes | No finding from previous release |
|
Development | Have all Defects of priority Highest and High been in status "Done" in Jira? | Yes | Jira |
---|
server | ONAP JIRA |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
maximumIssues | 20 |
---|
jqlQuery | project = CLAMP AND issuetype = Bug AND status in (Open, "In Progress", REOPENED, Submitted) AND priority in (Highest, High) |
---|
serverId | 425b2b0a-557c-3c0c-b515-579789cceedb |
---|
|
| No High or Highest Defects remaining |
Are all JIRA issues used as a reference in a commit in status "Done" in Jira? | Yes |
Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful. |
|
|
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours. | No |
|
|
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Yes | Link to |
Merge Job artifacts Nexus has the team addressed any issue (recorded in JIRA) provided by the Documentation team?Yes