AgendaMinutesSlides
SDC status in the sprint

general sync on the work

items being handled:

  1. CLM review and approval.
  2. UT coverage work on SDC.
  3. release creation for all the sdc components we are still missing the DCAE-DS.
  4. Request to add certificate to sdc Fronted server to solve the issue of using a mix communication in portal.
  5. plan to begin Dublin discussions in the flowing weeks.

Discussion about the Dublin arch/modeling F2F

presentations by Benjamin Cheung regarding impotent items coming pout of the meeting.


Q&Ageneral QA



SLIDES we discussed

View file
nameNFModeling-SDCR3-05Nov2018v7.pptx
height250

MAJOR TOPICS

  - 1. NF Modeling discussion

  - 2. ETSI / SOL1 Alignments & PNF onboarding

  - 3. Artifacts for FM/PM 

  - 4. Controller to NF association → PNF Model (SDC)


PNF ONBOARDING PROCESS & PACKAGE

The Wiki page describing the PNF ONBOARDING PROCESS & PNF PACKAGE is at:

PNF ONBOARDING

The slides presented are available from the 5G Use Case Dublin Page:

5G Use Case Sub Team Wiki (Dublin)

You can also reach the PNF Onboarding Wiki from the 5G U/C Dublin Page.



Action Items

...