  • Identified: a risk that has been identified, but has not yet been analyzed / assessed yet 
  • Assessed: an identified risk which currently has no risk response plan 
  • Planned: an identified risk with a risk response plan
  • In-Process: a risk where the risk response is being executed 
  • Closed: a risk that occurred and is transferred to an issue or the risk was solved/avoided
  • Not occurred: a risk that was identified but that did not occur 
  • Rejected: created and kept for tracking purposes but considered not to be used yet




Risk IDProject Team or person identifying the riskIdentification DateRisk (Description and potential impact)Team or component impacted by the risk

Mitigation Plan

(Action to prevent the risk to materialize)


Contingency Plan - Response Plan

(Action in case of the risk materialized)

Probability of occurrence (probability of the risk materialized)

High/Medium/Low

Impact

High/Medium/Low

Status
1SDNC1/14/19NETCONF/TLS support is new in OpenDaylight Fluorine release. Thus, ONAP will be one of the early adopters and hence there is some element of risk.SDNC/APPCWe will try to target NETCONF/TLS for an early sprint to allow ample recovery time if we need to fall back to NETCONF/SSH



215/01/19PNF use case being dependent on the delivery of the 5G use case, if it doesn't get deliver, then we won't be able to showcase the PNF use case in Dublin.CCSDK
CDS
SO



LowAssessed