The purpose of the exception request process is to enable projects and requirements owners to make a request to the TSC for an exception in the following cases:

  1. A project has missed been determined as NOGO at a milestone requirementcheckpoint, as determined by the release manager, but but the PTL believes that the project can complete the requirement and catch up to the regular schedule. Or, the project believes that it should be exempted from the requirement, altogether. 
  2. A proposed Use Case or Requirement has been determined by the release manager as NOGO at M1, based on code impact analysis provided by the effected components.  Howeverfailed to receive TSC approval at one of the milestone checkpoints. However, the use case or requirement owner disputes the analysis.

...