Comment: add July 13 TSC disposition on M1 review

...


ProjectPTLRelease Planning ArtifactsRelease Planning ChecklistTime UTCTSC Disposition
1ModelingHui DengRelease PlanningChecklist14:05Review approved w/ contingency resource allocation updates
2Service OrchestratorSeshu KumarRelease PlanningChecklist14:12Review approved w/ contingency resource allocation updates
3Multi VIM/CloudXinhui LiRelease PlanningChecklist14:19Review approved w/ contingency on resource allocation and action of risk section
4VNF RequirementsSteven Wright Release PlanningChecklist14:26-- not reviewed --
5CLIKanagaraj ManickamRelease PlanningChecklist14:33Review Approved
6Integration
Helen ChenRelease PlanningChecklist14:40Review Approved
7CCSDKDan TimoneyRelease PlanningChecklist 14:47Review Approved
8DMAAPRam KoyaRelease PlanningChecklist14:54

-- not reviewed – move to tsc meeting


9DocumentationRich BennettRelease PlanningChecklist15:01Review Approved
10External API FrameworkAndy MayerRelease PlanningChecklist15:08Review approved
11ONAP Operation ManagerDavid SauvageauRelease PlanningChecklist15:15

Review Approved w/ contingency on resource allocation and checklist


12Optimization FrameworkSarat PuthenpuraProject planned for Beijing Release. No need to be reviewed.15:22

-- Beijing release, not Amsterdam --


13Review of June 30, action items


15:29
14Network Function Change Management project proposalEmmanouil Mavrogiorgis

15:45Will be handled either as a subcommittee otr a use case for the Beijing release. Proposal is withdrawn.


Review Thursday, July 13


ProjectPTLRelease Planning ArtifactsRelease Planning ChecklistTime UTCTSC Disposition
1Virtual Infrastructure DeploymentAmichai HemliRelease PlanningChecklist14:05Project artifacts not complete. Required work. Catherine will lead the effort. Next review scheduled in July 20.
2Service Design & Creation
Eden Rozin (backing up Michael Lando)Release PlanningChecklist14:12

Approved with following to work on:

  • Add Architecture, API dependencies, scope and MVP.
3Logging EnhancementsLuke Parker (backing up Mark Pond)Release PlanningChecklist14:19

Approved

  • PTL to balance resource list
  • Provide an example of how project could use the log mechanism.
4Application Authorization FrameworkRam KoyaRelease PlanningChecklist14:26

Approved

  • PTL to evangelize his project to ensure adoption within ONAP community.
  • Team to discuss the "no" item in the checklist.
  • PTL to balance resource list
5DMAAPRam KoyaRelease PlanningChecklist14:33

Approved with following to work on:

  • PTL to balance resource list
6VNF RequirementsSteven Wright Release PlanningChecklist14:40
7

Approved with following to work on:

  • Fill out deliverables section
  • Integration plan requires clarification with Integration Team (Helen Chen)


F7University
Mazin Gilbert/
Nermin Mohamed
Update
Decision to update the community
on latest discussions/decisions
after meeting with LF on July 14.

14:47