Risk IDProject Team or person identifying the riskIdentification DateRisk (Description and potential impact)Team or component impacted by the risk

Mitigation Plan

(Action to prevent the risk to materialize)


Contingency Plan - Response Plan

(Action in case of the risk materialized)

Probability of occurrence (probability of the risk materialized)

High/Medium/Low

Impact

High/Medium/Low

Status
1ESRJuly 1st 2020The REQ-341 has dependency on ESR for updating the K8s cluster information.REQ-341To have the friends from Aarna network to help us in this functionality.In case ESR does not make it to Guilin, we will use the postman for updating the AAi with the detaisHighMedIn progress.
2SDCJuly 6th 2020The REQ-349 - Coverage of 55%SDCMinimize impact of changes to limit breakage of coverage metricswill request an exception for GuilinLowLow

Current metrics are at 54.8%, some sonar metrics do not show up on main page but are visible in details.

In Progress for improvments

3SDCJuly 6th 2020REQ 351 - Migration to Java 11SDCTry to get commitments from more companies to help on finishing the migrationwill request an exception for GuilinMediumLowMigration to Java 11 is well under way on main SDC project, still the complexity of project implies that there are several unknowns in completing this change
4OOFJuly 8, 2020Meeting non-functional requirements due to resource constraintsOPTF/CMSOTry to get commitments from potential contributerswill request an exception for GuilinHighLowRequesting commitments from more companies to meet the non-functional requirements