  • #AGREED The TSC approves Rc1, Rc2 and Sign-Off as all occurring on Nov. 19th
  • #AGREED the TSC meeting on Nov 26 will be cancelled due to the Thanksgiving holiday in the U.S.

October

 TSC  

  • TSC approved to cancel the TSC call on Oct 15th, 2020 (LFN DDF Fall Event) - #1853   (onap.org)
  • TSC approved kickoff date for Honolulu is end of day Oct 16th, 2020 i.e. Global requirements (functional and non functional requirements) to be available for the TSC to be reviewed and prioritized
  • TSC agreed that the AAI project contributes a concurrency bugfix to the Frankfurt branch on a few AAI microservices 

 TSC approved Configuration & Persistency Service (C&PS) to be an independent project - #1868   (onap.org)

...

  • TSC approves any requirement marked as "Green" as "GO" for M4

 

  • TSC approved projects that have completed their M4 tasks and exceptions for SO, VNFSDK, SDNC, AAI, MultiCloud and MSB to be completed by RC0 or earlier.
  • TSC approves the 2021 budget and priorities as set in LFN 2021 ONAP Project Inputs_V1.pdf, with the addition of the #info notes in the Zoom chat

 

  • TSC approves moving Guilin RC0 to Oct 12 and moving all remaining milestones by one week,with Sign-off will occur on Nov 12

August 

 

  • TSC agreed that only GPL v3 should be removed from the containers for the Guilin Release, distributed by the ONAP Community
  • TSC approves any requirement marked as "Green" and "Yellow" as "GO" for M2/M3 
  • TSC approved CLAMP, SDNC/CCSDK, Holmes projects as successfully passing their M2/M3 milestones.

...