2. New component capabilities for Honolulu, i.e. the functional enhancements


DCAE Focus for

...

R8 is on following

...

  • ONAP

...

  • R8 Usecase &

...

  • Feature requirement 

...

  • TSC/SECCOM

...

  • Global requirements

...

  • DCAE Transformation to support Helm deployment for services
  • General platform optimization (Cloudify upgrade for python 3.6)
  • Reducing DCAE backlogs

...

  •  + security fixes


Refer DCAE Honolulu Scope R8 M2 Release Planning#Scope for more details


Following new services will be delivered in R8 

...


In Honolulu, POC for

...

Event Processors

Analytics/RCA

Following service is retired for Honolulu

  • TCA (cdap)  - Replaced by TCA-gen2 (introduced in Frankfurt release)

For Honolulu, new MOD Front-End and Back-end components is being worked as PoCtracked under REQ-326 -Self Serve Control Loops will continue  - DCAEGEN2-2313 (this would eventually replace NiFI based UI/processor in subsequent ONAP release)


Image RemovedImage Added

3. New or modified interfaces

Architecture diagram - DCAE R8 M2 Release Planning#Highlevelarchitecturediagram

New External interfaces

  • Data Extraction Service API  - Provides basic computation and data retrieval/access from datastorage maintained by DL handlers (Feeder). This API will be consumed by Slice Analysis MS (DCAE) and UUINone for H release

Modified interfaces

  • VES Collector (7.2 VES support)

...

Relies on k8s for loadbalancing and scaling. DCAE platform handles the control flow and do not carry the data/event; DCAE service components can be scaled and support state management through external DB and/or K8S state management.
Cloudify is 3rd party product; multi-site feature on community version will be available later in 2020; will be incorporated for G release.


As DCAE collectors are extensively used in all ONAP usecase, performace testing has been done on below collectors

...

8. Platform Maturity Targets

DCAE R8 M2 Release Planning#PlatformMaturity.1

Global Requirement and Best Practices 

DCAE R8 M2 Release Planning#BestPracticeCandidates

Non-Functional - DCAE R8 M2 Release Planning#Non-FunctionalRequirementPlanning#GlobalRequirements

9. Listing of new or impacted models used by the project (for information only)

Support for new policy model as required by Model driven control loop requirement.VES Mode updates tracked under REQ-433 - ONAP/3GPP & O-RAN Alignment-Standards Defined Notifications over VES (Honolulu)