Agenda:

  1. Guilin Maintenance Release status:
    • For CCSDK/SDNC, Guilin maintenance release contains fixes for transport slicing use case:
      • Jira
        serverONAP JIRA
        columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
        serverId425b2b0a-557c-3c0c-b515-579789cceedb
        keyCCSDK-3075
      • Jira
        serverONAP JIRA
        columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
        serverId425b2b0a-557c-3c0c-b515-579789cceedb
        keySDNC-1431
    • Release builds created for CCSDK and SDNC, and helm charts have been updated. 
    • Only remaining item is certificate refresh for cds-ui
  2. Honolulu Release status
  3. M1 milestone scheduled for next Monday (1/11/21)
  4. Next milestone (M2 / Spec Freeze) scheduled for 1/21/21
    • CCSDK and SDNC were both approved as passed M2 (Spec Freeze) milestone at special TSC meeting 1/25.  Release planning templates :
    • Issue discovered in docker builds in master branch:
      • Had been using initial Honolulu release version of ccsdk/sli instead of snapshot version
      • Fix for this uncovered another issue with ccsdk/sli, caused by a refactoring change.
      • Refactoring change has been reverted for now until it can be verified in local environment
    • ODL Aluminum port underway:
      • Doing local testing to verify that docker container comes up clean before merging changes.
    • Next project milestone is M3 - Feature Freeze:
      • TSC vote scheduled for  
        • M3 criteria includes that all release builds must be complete and helm charts must be updated in OOM to deliver released dockers
        • To allow time for code reviews, release builds and OOM review, final code reviews for CCSDK and SDNC Honolulu should be submitted no later than  
  5. Open Discussion