Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Tasks/DeliverablesMost ProjectsVVPVNFREQINT
All high/highest priority jira tickets (bugs) addressed(tick)(tick)(tick)(tick)
Remaining License scan, security critical issues addressed(tick)(tick)(tick)(tick)
Update Release note and documentation(tick)(tick)(tick)(tick)
Docker images “Release” dues (tick)(tick)(error)(error)
Project specific test plan completed(tick)(error)(error)(error)
Update Frankfurt Risks(tick)(error)(tick)(tick)
Integration Weather Board complete(tick)(error)(error)(tick)
Versioning at the project level(tick)(tick)(error)(tick)
Check the certification expiry of your application. It should be valid for the next 9 months after RC0. (tick)(error)(error)(error)
CI Daily for Release(error)(error)(error)(tick)




















RC1 (TBD)

Tasks/DeliverablesMost ProjectsVVPVNFREQINT
  • JIRA
    • All stories, epics, tasks, and subtasks (except documentation) should be closed
    • All high/highest priority
jira tickets (bugs) addressed
    • tickets opened since RC0 should be closed
(tick)(tick)(tick)(tick)
Remaining License scan, security critical issues addressed
Docker image release including bug fixes(tick)(tick)
(tick)
(error)
(tick)Update Release note and documentation(tick)(tick)(tick)(tick)Docker images “Release” dues (tick)(tick)(error)(error)Project specific test plan completed(tick)(error)(error)(error)Update Frankfurt Risks(tick)(error)(tick)(tick)Integration Weather Board complete(tick)(error)(error)(tick)
(error)
Integration test status updated with % complete and estimated days to completion (integration test status page)(error)(error)(error)(tick)
CI Daily for Release(error)(error)(error)(tick)

RC2 (TBD)

Tasks/DeliverablesMost ProjectsVVPVNFREQINTDocumentation
  • JIRA
    • All stories, epics, tasks, and subtasks (except documentation) should be closed
    • All high/highest priority tickets opened since RC1 should be closed
(tick)(tick)(tick)(tick)(error)
  • Finalize documentation
    • Release notes, including security waivers
(tick)(tick)
Versioning at the project level
(tick)(tick)(error)
(tick)Check the certification expiry of your application. It should be valid for the next 9 months after RC0.
Final docker image(tick)(tick)(error)(error)(error)
Integration Release test status shows 100% completed and zero days remaining for testing(error)
(tick)
(error)(error)(tick)(error)
CI Daily for Release(error)(error)(error)(tick)(error)
  • Publish release documentation
    • Frankfurt branch for RTD
    • Update main page to Frankfurt, including version number
(error)(error)(error)(error)(tick)

Sign-off

  • Remaining high/highest priority jira tickets addressed or workaround documented
  • Close/move all open/in-process jiras to a future release
  • Integration "Sign-Off" on Docker images “Release” 
  • Release notes and documentation completed
  • OOM tag release and version in helm chart
    Update the Frankfurt Release Key Updates