The page is intended to summarize all the requirements for Guilin Release.

Candidate requirement proposals were frozen on May 28, 2020 TSC 2020-05-28

These requirements have been prioritized by the TSC to realistically fit within the Guilin Release

...

on June 25th, 2020.

The Release Scope

...

was finalized during the M1 Release Planning milestone on

...

July 16th, 2020

Note:  we will no longer be using a Confluence table to track requirements. More information here.

Associated integration test tasks may be found here:  2: Guilin Release Integration Testing Status

TSC

...

Prioritization (Ranking)

  • RANK #0  – Special GO - quick wins, fully covered by involved companies
  • RANK #1 – TSC Must Have – Mandatory for the release
  • RANK #2 – Continuity  - Items continued from previous releases
  • RANK #3 – PTL Go – items that PTLs is OK to include since team has bandwidth
  • RANK #4 – NO GO OR Not yet Reviewed by TSC – items not approved for various reasons

...

Requirements Milestones Summary

See also Documenting Release Requirements in JIRA

Jira Charts
serverONAP JIRA
jqlproject%20%3D%20REQ%20and%20issuetype%20%3D%20Task%20and%20%22Epic%20Link%22%20!%3D%20REQ-1
ystattypecustomfield_10001
chartTypetwodimensional
isAuthenticatedtrue
numberToShow25
xstattypeallFixfor
serverId425b2b0a-557c-3c0c-b515-579789cceedb

Use Cases 

Release 6 (Guilin) proposed use cases and functional requirements

M1 Scorecard:

  • Green: Use Case will be fully implemented and tested
  • Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
  • Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.

Architecture:

...

...

numberOfFixedRows1
numberOfFixedColumns4
decimalMark. (point)

...

JIRA link (REQ)

One issue per requirement.

Instructions

...

M1

Scorecard

...

T-Shirt Size (star)

...

Committed (C)/ Partially Committed (P) or not (N) per impacted project

...

Company

Engagement

...

T-Shirt Size

...

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Requirements

...

Milestone Scorecard (except M1)

  • Green:

...

  • On Track
  • Yellow:

...

Architecture:

  • Pink - NO  GO
  • Purple - GO
  • Green- Considered OK not requiring architecture review
  • Black - Architecture not yet performed

...

numberOfFixedRows1
numberOfFixedColumns4
decimalMark. (point)

...

JIRA link (REQ)

One issue per requirement.

Instructions

...

  • Use Case/Requirement not on track but could be mitigated by reducing the current scope and/or fix this issue prior M4. Risks identified and documented under Guilin Risks  
  • Red: Use Case/Requirement not on track and issue identified that will prevent from completing the development by M4. Use Case/Requirement should be moved to POC in alignment with the POC definition or de-scoped from the Guilin release.

Guilin Use Cases

Jira
serverONAP JIRA
columnskey,summary,assignee,arch review,tsc priority,scope status,t-shirt size,m1 scorecard,m1 approval,m2/3 scorecard,m2/3 approval,m4 scorecard,m4 approval,rc0 scorecard,rc0 approval,status
maximumIssues1000
jqlQueryfilter=12312
serverId425b2b0a-557c-3c0c-b515-579789cceedb


Guilin Requirements

Jira
serverONAP JIRA
columnskey,summary,assignee,arch review,tsc priority,scope status,t-shirt size,m1 scorecard,m1 approval,m2/3 scorecard,m2/3 approval,m4 scorecard,m4 approval,rc0 scorecard,rc0 approval,status
maximumIssues1000
jqlQueryfilter=12311
serverId425b2b0a-557c-3c0c-b515-579789cceedb

Guilin Non-Functional Requirements

Jira
serverONAP JIRA
columnskey,summary,assignee,arch review,tsc priority,scope status,t-shirt size,m1 scorecard,m1 approval,m2/3 scorecard,m2/3 approval,m4 scorecard,m4 approval,rc0 scorecard,rc0 approval,status
maximumIssues1000
jqlQueryfilter=12313
serverId425b2b0a-557c-3c0c-b515-579789cceedb

Guilin PoC

Jira
serverONAP JIRA
columnskey,summary,assignee,scope status,t-shirt size,status
maximumIssues20
jqlQueryfilter=12314
serverId425b2b0a-557c-3c0c-b515-579789cceedb

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

POC / Experimentation

POC definition

...

numberOfFixedRows1
numberOfFixedColumns4
decimalMark. (point)

...

(star)T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team

...