REQ# | DCAE Commit Status | DCAE Impact Assessment | DCAE JIRA # |
TBC | CertService client integration (replacing init container) + auto certificate reload via SDK Commitment from Nokia |
...
REQ# | DCAE Commit Status | DCAE Impact Assessment | DCAE JIRA # |
REQ-715 - Bulk PM / PM Data Control Improvements | YES | PMSH enhancement for dynamic filter/subscription change + API enhancements Commitment from Ericsson | |
DCAEGEN2-2703 Add stndDefined domain to HV-VES | YES | Add stndDefined support in HV-VES Commitment from Nokia | DCAEGEN2-2703 |
DCAEGEN2-1483 - VESCollector synchronous handling (Backlog) | YES | VESCollector Enhancements – Event publish order issue Commitment from Nokia | |
DCAEGEN2-2668 - MOD Enhancements (Backlog) | Stretch | Address backlog items identified from previous release (Catalog/authservice/UI)
|
...
Istanbul POC (DCAE impact)
REQ# | DCAE Commit Status | DCAE Impact Assessment | DCAE JIRA # |
REQ-685 - DCAE Transformation to support Helm (Phase2) | YES |
Commitment from AT&T, Nokia, Ericsson, Wipro, Independent, Orange/Samsung (OOM) |
...
REQ# | DCAE Commit Status | DCAE Impact Assesment | DCAE JIRA # |
REQ-443 - CONTINUATION OF CII BADGING SCORE IMPROVEMENTS FOR SILVER LEVEL | Stretch-goalYES | Sonar security fixes (RESTConf) CII badging score improvement | DCAEGEN2-2829 |
REQ-439 - CONTINUATION OF PACKAGES UPGRADES IN DIRECT DEPENDENCIES | YES | Tcagen2, DFC, RESTConf, MOD-runtimeAPI, Mapper, PM-Mapper, PRH, SON-Handler, KPI-Computation MS, Slice-Analysis MS | DCAEGEN2-2768 |
REQ-437 - COMPLETION OF PYTHON LANGUAGE UPDATE (v2.7 → v3.8) | YES | HealthCheck container | DCAEGEN2-2737 |
REQ-438 - COMPLETION OF JAVA LANGUAGE UPDATE (v8 → v11) | No |
Exception will be filed with SECCOM for waivers due to upstream (NIFi) dependency | |
REQ-432 - IPv4/IPv6 dual stack support in ONAP | YES | Enhance ONAP common-service template - add IPv4/IPv6 support Commitment from Nokia | OOM-2749 |
...
Target Architecture (REQ-685)
Platform Maturity
Istanbul Release Platform Maturity
Refering to 2017-06-28 CII badging for ONAP.pptx and Platform Maturity Requirements (aka Carrier Grade), fill out the table below by indicating the actual level , the targeted level for the current release and the evidences on how you plan to achieve the targeted level.
...
API Name | API Description | API Definition Date | API Delivery date | API Definition link (i.e.swagger) |
---|---|---|---|---|
VES Collector | API for VNFs to send VES data | Currently Available | No change for this release | |
DCAE Deployment Handler | NB API for invoking the deployment of DCAE subcomponents | Currently Available | R3 | No change for this release |
DCAE Inventory | API for Add/Delete DCAE copy's TOSCA models | Currently Available | R3 | No change for this release |
Healthcheck | API for querying DCAE component healthcheck | Currently Available | R4 | No change for this release |
DCAE Onboarding API | API for publishing DCAE spec into MOD | Currently Available | R6 | No change for this release |
DCAE Inventory | API for CLAMP to retrieve flow information | Currently Available | R6 | No change for this release |
Data Extraction Service (DES) | API for data retrieval and simple computation from DL-Handler maintained storages (For R8, this will be used by DCAE components such Slice-Analyis MS) and UUI | Currently Available | R8 | No change for this release |
PMSH | API support for Subscription/Filters/Measurement group management | Under review (https://gerrit.onap.org/r/c/dcaegen2/+/121898) | R9 M2 | https://gerrit.onap.org/r/c/dcaegen2/+/121898 |
SliceAnalysis | API support for data aggregation based on NSI/NSSI; this will be consumed by OOF | Reviewed | R9 M2 | NSI/NSSI Selection based on resource occupancy levels |
Third Party Products Third Party Products Dependencies
Third Party Products mean products that are mandatory to provide services for your components. Development of new functionality in third party product may or not be expected. List the Third Party Products (OpenStack, ODL, RabbitMQ, ElasticSearch,Crystal Reports, ...).
...
The milestones are defined at the Release Planning: HonoluluIstanbul and all the supporting project agreed to comply with these dates.
...
Date | Sprint | #No of days | Deliverable | ||
---|---|---|---|---|---|
Key dates for Istanbul release - M1 - 05/20, M2 - 06/17, M3 - 08/26, M4- 09/16, RC - 10/14,Signoff - 10/28 | |||||
0105/0420/2021 2021 - 0106/2117/2021 | DCAE Honolulu Istanbul Sprint 1 (Planning)14 |
| |||
06/1801/22/2021 - 02 07/1115/2021 | DCAE Honolulu Istanbul Sprint 2 (Development)15 |
| |||
0207/1216/2021 2021 - 03 08/0426/2021 | DCAE Honolulu Istanbul Sprint 3 (Code Freeze) | 15 | M3 - 2 weeks dev + package finalization (container released)
| ||
0308/0527/2021 2021 - 03 09/2516/2021 | DCAE Honolulu Istanbul Sprint 4 (Integration support)Container Release/artifact) | Finalize containers/jars for Istanbul release and submit patch to OOM for revisions | |||
09/17/2021 - 10/14/2021 | Integration | 15 | M3 - |
|
Documentation, Training
- Highlight the team contributions to the specific document related to he project (Config guide, installation guide...).
- Highlight the team contributions to the overall Release Documentation and training asset
- High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
- Documentation includes items such as:
- Installation instructions
- Configuration instructions
- Developer guide
- End User guide
- Admin guide
Honolulu Istanbul Documentation
Other Information
Vendor Neutral
...