El Alto Release Management
M1 -
...
> Sign-Off
Jira Charts | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Jira Charts | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
M1→Sign-off Feedback (10/
...
24):
- Congrats APPC, VID, MUSIC, Portal, Policy, MSB, DMaaP, ExtAPI, VNFReqs, VVP, SDNC and CCSDK Teams - Ready for sign-off
- UUI - waiting confirmation to be descoped
- Portal SDK 2.6.0 will not be integrated into impacted components i.e. CLAMP, VID, PORTAL etc.
...
- Update Release note and documentation
- Versioning at the project level
...
- All high/highest priority jira tickets to be addressed -
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key AAF-986
...
- Project specific test plan for El Alto to be completed
- All high/highest priority jira tickets to be addressed
...
- All high/highest priority jira tickets to be addressed
- Complete pair-wise testing and update Integration Weather Board
- Docker images “Release” dues
- Versioning at the project level
...
- All high/highest priority jira tickets to be addressed - NEW on 10/3
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key CCSDK-1793
...
- All high/highest priority jira tickets addressed -
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key DCAEGEN2-1757
...
- Request PTL to review all the Release Management Tickets
...
- All high/highest priority jira tickets addressed
...
- Update Release note and documentation
- Versioning at the project level
...
- Complete pair-wise testing and update Integration Weather Board
...
- All high/highest priority jira tickets addressed
- Versioning at the project level
- Complete pair-wise testing and update Integration Weather Board
...
- All high/highest priority jira tickets addressed
- Request PTL to review all the Release Management Tickets
...
- All high/highest priority jira tickets addressed
- Complete pair-wise testing and update Integration Weather Board
...
- All high/highest priority jira tickets addressed -
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key SDC-2541
...
- All high/highest priority jira tickets addressed
- Remaining License scan, security critical issues addressed
...
- Request PTL to review all the Release Management Tickets
...
- All high/highest priority jira tickets addressed
...
- ONAP Community !!! The ONAP TSC has signed-off on the El-Alto Release on 10/24.
- Portal SDK 2.6.0 will not be integrated into impacted components i.e. CLAMP, VID, PORTAL etc.
...
El Alto Final Release (5.0.1)
...