Agenda Items | Notes |
---|---|
Logistics | M4 milestone was moved to 9/28. Let's discuss impacts to each sub-team. Amsterdam is delayed 2 weeks |
Action items from last week | Should we ask TOSCA to deprecate option 1? Note: Not for Release 1 - discussion is long-term. Andrei, Alex and Thinh participate. Alex indicates TOSCA will not deprecate this. How about asking ETSI NFV team changing the wording in SOL004? They could tighten the requirements Or go to VNF requirements package ONAP project and ask them to tighten up the requirements. We should address this in ONAP regardless of whether we take this back to ETSI or OASIS. Going to ETSI may be counterproductive as those participating companies voted to keep Option 1. Option 1 is meta data type. Both options should support manifest files. |
Sprint 3 Progress |
|
Preparation for Sprint 4 |
Sprint 4 definition: Andy: -21, To be discussed on next call. Victor: Not present Validation: Not present Lianhao: -52, -35 |
Any blockers or open issues that need to be addressed? | Harry: VNFSDK and OPNFV Automation relationship? What is the motiviation of the question? Need to clarify. Alex: Leverage certification tests for VNFs from OPNFV for the ONAP Marketplace. There is someone on the liaison page for the OPNFV community. VNF SDK is for VNF developers and platform integrators. There shouldn't be an overlap |
...