Key points of Contact for Lab/component deployment:

Lab/ComponentNameEmail Notes
 POD-25

 Stephen Gooch

Gil Hellmann

 stephen.gooch@windriver.com>

gil.hellmann@windriver.com

 


AAIJimmy Forsythjf2512@att.com
 

ESRZi Lili.zi30@zte.com.cn
 

APPC

Aaron Hay

Veer Rajasekhar

ah415j@att.com

vr772b@att.com

 


CDP-PALTyler Smithts4124@att.com>  9/6/17: CDP-PAL is deployed as part of APPC. APPC team will pull in Tyler as needed.
 MultiVIM Bin Yang Bin.Yang@windriver.com
 

 Reference VNF Marco Plantania platania@research.att.com 9/6/17: Need to confirm with Marco that he will be the contact/support point for this.

Component Specs:

ComponentVM

vCPU/

Cores

 RAMStorageAdditional Details
AAI28 16GB50GBan additional volume of 50 GB
ESR12 ?N/AESR uses AAI for storage
APPC/CPD-PAL14 8GB80GB
MultiVIM? ? ??
VNF (vFW
) 
)





Deployment order:

  • From a deployment sequence, we assume the following order:
    • AAI (and ESR - look to AAI for details on deployment dependencies between these AAI & ERS microservice)
    • APPC (checks for AAI availability, so needs to come after AAI)
    • MutlVIM
    • VNF

High Level Tests: To be also tracked in Integration project

  • Via apidoc explorer
    • LCM Restart
    • <TBP >

Timeline:Timeline

9/7/17:

  • Lab planning activities to start this week (9/7)- led by Gil Hellman, who will reach out to key contacts from above.
  • APPC and AAI should have code done by end of week (9/8), so dockers may need to be upgraded next week depending on deployment progress made this week.
  • We will checkpoint early next week to see if we are ready to start testing; lab deployments always take longer than anticipated due to various issues related to connectivity that come up.  

...