High Level Tests: To be also tracked in Integration project
...
- APPC
No. | Description | JIRA | ||||||||
---|---|---|---|---|---|---|---|---|---|---|
1 | APPC ONAP -LCM API HEALTHCHECK |
| ||||||||
2 | APPC ONAP -LCM API VM RESTART |
| ||||||||
3 | APPC ONAP -LCM API VNF RESTART |
| ||||||||
4 | APPC ONAP -LCM API START |
| ||||||||
5 | APPC ONAP -LCM API STOP |
| ||||||||
6 | APPC ONAP -LCM API VM REBUILD |
|
...
Timeline:
9/6/17:
- Lab planning activities to start this week (9/7)- led by Gil Hellman, who will reach out to key contacts from above.
- APPC and AAI should have code done by end of week (9/8), so dockers may need to be upgraded next week depending on deployment progress made this week.
- We will checkpoint early next week to see if we are ready to start testing; lab deployments always take longer than anticipated due to various issues related to connectivity that come up.
...