High Level Tests: To be also tracked in Integration project

  • APPC
No.DescriptionJIRA
1

APPC ONAP -LCM API HEALTHCHECK

Jira
showSummaryfalse
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyINT-205

2

APPC ONAP -LCM API VM RESTART

Jira
showSummaryfalse
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyINT-206

3

APPC ONAP -LCM API VNF RESTART

Jira
showSummaryfalse
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyINT-207

4

APPC ONAP -LCM API START

Jira
showSummaryfalse
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyINT-208

5

APPC ONAP -LCM API STOP

Jira
showSummaryfalse
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyINT-209

6

APPC ONAP -LCM API VM REBUILD

Jira
showSummaryfalse
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyINT-210

Timeline:

9/6/17:

  • Lab planning activities to start this week (9/7)- led by Gil Hellman, who will reach out to key contacts from above.
  • APPC and AAI should have code done by end of week (9/8), so dockers may need to be upgraded next week depending on deployment progress made this week.
  • We will checkpoint early next week to see if we are ready to start testing; lab deployments always take longer than anticipated due to various issues related to connectivity that come up.  

...