Risk IDProject Team or person identifying the riskIdentification DateRisk (Description and potential impact)Team or component impacted by the risk

Mitigation Plan

(Action to prevent the risk to materialize)


Contingency Plan - Response Plan

(Action in case of the risk materialized)

Probability of occurrence (probability of the risk materialized)

High/Medium/Low

Impact

High/Medium/Low

Status
1ESRJuly 1st 2020The REQ-341 has dependency on ESR for updating the K8s cluster information.REQ-341To have the friends from Aarna network to help us in this functionality.In case ESR does not make it to Guilin, we will use the postman for updating the AAi with the detaisHighMedIn progress.
2SDCJuly 6th 2020The REQ-349 - Coverage of 55%SDCMinimize impact of changes to limit breakage of coverage metricswill request an exception for GuilinLowLow

Current metrics are at 54.8%, some sonar metrics do not show up on main page but are visible in details.

In Progress for improvments

3SDCJuly 6th 2020REQ 351 - Migration to Java 11SDCTry to get commitments from more companies to help on finishing the migrationwill request an exception for GuilinMediumLowMigration to Java 11 is well under way on main SDC project, still the complexity of project implies that there are several unknowns in completing this change
4OOFJuly 8, 2020

Meeting non-functional requirements due to resource constraints

OPTF/CMSOTry to get commitments from potential contributerscontributorswill request an exception for GuilinHighMediumLowRequesting commitments from more companies to meet the non-functional requirements

Code coverage and security vulnerability fix are done. 

REQ-358 is pending

5DCAEJuly 8, 2020

Meeting non-function requirements - REQ-379 (approved base image) complaince 

DCAE
  • Finalize approved base image ASAP
  • Resource committment required from multiple companies due to number of components involved
Will be worked in-phase and need exception for components not migratedHighLowIdentified
6DCAEJuly 8, 2020

DCAE being large project with 40+ component, need more time for complaince with non-functional requirements - REQ-366 & REQ-365 

DCAEHave commitment from Ericsson; more contributors will help mitgating the risk  Will be worked in-phase and need exception for components not compliantMediumMediumIdentified
7DCAEJuly 8, 2020

Resource/time constraint for supporting  nonfunctional REQ-351 (Java11 upgrade).

Some MOD components will need exception (due to NiFI upstream dependency)


DCAE

More companies to help with migration

Will be worked in-phase and need exception for components not migrated.

MediumLowIdentified
8PortalJuly 8, 2020

Meeting the following Non-Functional Priority 1 and 2 Requirements

https://jira.onap.org/browse/REQ-380
https://jira.onap.org/browse/REQ-379
https://jira.onap.org/browse/REQ-366
https://jira.onap.org/browse/REQ-362
https://jira.onap.org/browse/REQ-351
https://jira.onap.org/browse/REQ-357
https://jira.onap.org/browse/REQ-356
https://jira.onap.org/browse/REQ-386

PortalNeed support from communityPhased approach and file exceptions for the items that cannot be delivered or picked up by communityHighMediumIdentified
9HolmesJuly 9, 2020

There's no env for the team to carry out any functional tests. Due to the network restriction in our company, we have no access to the WindRiver lab, so it seems impossible for us to do any tests after code modifications. This would impact the integration with AAF.

HolmesTrying to apply for HW resources to build up a testing env within our company.will request an exception for GuilinMediumMediumIdentified
10SDCJuly 9, 2020

Meeting non-functional requirements - 

REQ-366 & REQ-365 

SDCNeed support from communityPhased approach and file exceptions for the items that cannot be delivered or picked up by communityHighMediumIdentified
11MultiCloudJuly 9, 2020Meeting non-functional requirements -  REQ-373 , REQ-363 , REQ-351REQ-349 , MultiCloudNeed support from communityWill request waiver in Guilin releaseHighMediumIdentified
12AAIJuly 9 2020AAINeed support from communityWill request waiver in Guilin releaseHighMediumIdentified
 13MSB July 15th Can not meet REQ-351 lack of capacity MSB Need support from communityWill request waiver in Guilin release High HighIdentified 
 14Modeling July 15th  Can not 

Meeting non-functional requirements -

REQ-379, , REQ-366, REQ-365, REQ-362, , REQ-351

 

 Modeling Need support from community Will request waiver in Guilin release HighHigh Identified 
 15 VID July 15th  Can not Meeting non-functional requirements - REQ-361 VID Need support from communityWill request waiver in Guilin release High High Identified 
 16 VF-C July 15th  

 

Can not 

Meeting non-functional requirements -

REQ-

351, 365, 366
 VF-CNeed support from community Will request waiver in Guilin release High High Identified 
17PolicyJuly 23 2020Meeting non-function requirements - REQ-379 (approved base image) compliance Policy

Need finalized approval base image ASAP, in order to request the resource from community

Will request waiver in Guilin releaseHighLowIdentified 

...