Project Name | Enter the name of the project |
---|---|
Target Release Name | Honolulu |
Project Lifecycle State | Mature. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information |
Participating Company | AT&T, Nokia, Ericsson, Wipro, ChinaMobile, T-Mobile |
Scope
What is this release trying to address?
...
REQ# | DCAE Commit Status | DCAE Impact Assesment | DCAE JIRA # |
REQ-438 - COMPLETION OF JAVA LANGUAGE UPDATE (v8 → v11) | YES | Require exception for MOD/genprocessor/designtool/nifi-registry Risk #6 (Honolulu Risks) | |
REQ-437 - COMPLETION OF PYTHON LANGUAGE UPDATE (v2.7 → v3.8 | YES |
Commitment from T-mobile, Independent contributon Risk #7 (Honolulu Risks) |
...
Testing and Integration Plans
- Unit Test addition will be enforced part of new code submission; all components are required to maintain 55% codecoverage at the minumum.
- Functional test plan
- CSIT tests will continue to be supported for existing componentsPairwise testing will be done in the WindRiver Dev lab similar to what was done in last releasecomponents and new components
- DCAE has number of CSIT - https://jenkins.onap.org/view/CSIT/; these will be continued to be validated during course of development for this release.
- Pairwise testing will be done in the WindRiver Dev lab; below wiki page captures the test planned
- DCAE also has number of Smoke test (Example - https://logs.onap.org/onap-integration/daily/onap_daily_pod4_master/01-18-2021_08-01/) enabled for several components/flows; these test are validated part of gating for new container releases
- Bulk-PM
- HV-VES
- VES
- PRH flow
Gaps
This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release. List identified release gaps (if any), and its impact.
...