Date

Attendees

Discussion items

  • New ship date is due to material constraints 
  • ~ 2 days rack/stack estimate after receipt of HW 
  • No UNH lab activity will occur between Christmas and start of the new business year
  • Intel also impacted by supply chain - existing servers being in use is not a blocking issue for Intel at this time.