The following items are expected to be completed for the project to Pass  Release Sign-Off Milestone.

Release Sign-Off Milestone overview is available in wiki.


Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)
Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre committed Product Backlog Stories been coded and marked as "Closed" in Jira?In progress

Are all tasks associated with committed Product Backlog Stories been marked as "Closed" in Jira?In progressLink to Jira
Provide the project features list under the form of a bulleted list.In progressLink to evidence

Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off

In progress

Release ManagementHave all issues pertaining to FOSS been addressed?Yes

Have all findings from previous milestones been addressed?Yes

DevelopmentAre all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

Are all binaries available in Nexus Release repository?Yes

SDC-TOSCA

SDC-DISTRIBUTION-CLIENT


Are all Docker images available In Nexus?Yes

SDC

WORKFLOW

DCAE-DS


Are the Java and Docker manifest updated with the same version as in Nexus Release repository?Yes

DCAE-DS

SDC

WORKFLOW


Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?Yes

Has the project code successfully passed the Daily Build process?YesJenkins external lab report

Has the project done the integration testing with related dependent projects?

Yes*As of today there are CCVPN specific issues that are failing between SDC to UUI and SO. as sdc is not commited to this in the release the are not blocking.
Documentation

Has your team contributed and completed work in the following documentations in ReadTheDocs:

  1. Release Notes
  2. Project Documentation
In progress