Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Closed" in Jira?YesHolmes Backlog

Have all findings from previous milestones been addressed?NA

DevelopmentHave all Defects of priority Highest and High been in status "Closed" in Jira?Yes

HOLMES-178 - Getting issue details... STATUS


Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?Yes
Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

Are all the Jenkins jobs successfully passed (verify + merge jobs)?YesProvide link to "Merge job" as evidence in Jenkins project tab

Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes
Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?No

The CSIT is failing in the remote environment, but everything works fine when I fetch the latest release of Holmes and run it locally.

I'm still troubleshooting with Gary to figure out a way to bring the job back to normal. It needs some time, but it does not impact Holmes functionalities since it's just an environmental issue for the CSIT job.


At RC0, has the Pair Wise testing table been filled out?NACasablanca Pair Wise Testing master page
At RC0, have all OOM Release Healtcheck related to your project passed?NA

At RC0, is there a Docker image in Nexus Docker-Release repo available for each repository?NA

Has the project code successfully passed the Daily Build process?Yes
Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?Yes

Has the Heat deployment passed?

(not a gating item for Casablanca)

NA

Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


NA

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

NA

For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?

Yes

For RC2, has the Documentation Team provided the final approval for your project documentation?