The page is intended to summarize all the requirements for Guilin Release.
These requirements have been prioritized by the TSC to realistically fit within the Guilin Release Timeline.
The Release Scope should be finalized during the M1 Release Planning milestone on TBD
TSC Prioritization (Ranking)
- RANK #0 – Special GO - quick wins, fully covered by involved companies
- RANK #1 – TSC Must Have – Mandatory for the release
- RANK #2 – Continuity - Items continued from previous releases
- RANK #3 – PTL Go – items that PTLs is OK to include since team has bandwidth
- RANK #4 – NO GO – items not approved for various reasons
Requirements Milestones Summary
See also Documenting Release Requirements in JIRA
Epic Link | Fix For Versions (all) | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Frankfurt Release | Guilin Release | Honolulu Release | Istanbul Release | Jakarta Release | Kohn Release | London Release | Montreal Release | New Delhi Release | Istanbul Maintenance Release 1 | Unscheduled | T: | |
5G / OOF SON Enhancement | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
5G / ORAN & 3GPP Standards Harmonization | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
5G OOF SON use case requirements for Guilin release | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 |
5G Service Modeling in R8 | 0 | 0 | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 17 |
5G SON use case enhancements for Istanbul release | 0 | 0 | 0 | 13 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 13 |
5G SON use case enhancements for Jakarta release | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 0 | 0 | 0 | 14 |
5G SON use case enhancements for Kohn release | 0 | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 0 | 0 | 14 |
5G SON use case enhancements for London release | 0 | 0 | 0 | 0 | 0 | 0 | 14 | 0 | 0 | 0 | 2 | 16 |
5G SON Usecase R8 | 0 | 0 | 16 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 18 |
A1 Adapter Extension & A1 Policy Management | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 |
A1 Policy Functions Extension - Istanbul | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
A1 Policy Functions Extension - Jakarta | 0 | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
A1 Policy Functions Extension - Kohn | 0 | 0 | 1 | 1 | 1 | 13 | 0 | 0 | 0 | 1 | 0 | 13 |
A1 Policy Functions Extension - London | 0 | 0 | 0 | 0 | 0 | 0 | 13 | 0 | 0 | 0 | 0 | 13 |
Add VSP Compliance and Verification Check feature Phase 2 | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
Akraino Distributed Analytics use case | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
All Control Loop Policy Models should be TOSCA Compliant | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
APPC Ansible automation with VNF-C LCM support | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
Architecture - modelling alignment | 7 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 7 |
ASD onboarding package IM / DM | 0 | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
Bulk PM / PM Data Control Extension | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 |
Bulk PM / PM Data Control Improvements | 0 | 0 | 11 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 11 |
Bulk PM / PM Data Control Improvements | 0 | 0 | 0 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 |
Bulk PM / PM Data Control Improvements | 0 | 0 | 0 | 0 | 13 | 0 | 0 | 0 | 0 | 0 | 0 | 13 |
CCVPN-E-LINE Service over OTN NNI | 3 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
Total Unique Issues: | 196 | 22 | 248 | 184 | 189 | 107 | 187 | 1 | 1 | 1 | 84 | 1216 |
Use Cases
Release 6 (Guilin) proposed use cases and functional requirements
M1 Scorecard:
- Green: Use Case will be fully implemented and tested
- Yellow: Use Case will be partially implemented. It is possible to identify capabilities for this use case that can be tested (phasing approach).
- Red: Use Case can not be partially delivered, min. requirements can not be met in order to define a testing strategy.
Architecture:
- Pink - NO GO
- Purple - GO
- Green - Considered OK not requiring architecture review
- Black - Architecture not yet performed
Use Case | JIRA link (REQ) One issue per requirement. | Owner(s) | TSC Ranking | M1 Scorecard | TSC M1 Approval | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size | Project's Impact: Test Only (TO), Code (C) | Committed (C)/ Partially Committed (P) or not (N) per impacted project | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Integration Lead | Company Engagement | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
Requirements
M1 Scorecard:
- Green: The requirement will be fully implemented and tested
- Yellow: The requirement will be partially implemented. It is possible to identify capabilities for this functional requirement that can be tested (phasing approach).
- Red: The requirement can not be partially delivered, min. requirements can not be met in order to define a testing strategy
Architecture:
- Pink - NO GO
- Purple - GO
- Green- Considered OK not requiring architecture review
- Black - Architecture not yet performed
Requirement | JIRA link (REQ) One issue per requirement. | Owner | TSC Ranking | M1 Scorecard | TSC M1 Approval | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size (XS, S, M, L, XL) | Project's Impact: Test Only (TO), Code (C), Documentation Only (DO) | Committed (C)/Partially Committed (P) or not (N) per Impacted projects | If Partially or not Committed, what are gaps/ project (people/FTEs; HLD/LLD; etc) | Integration Lead | Company Engagement | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.
POC / Experimentation
Type | Requirement | Owner | Link(s) to HLD/LLD if any | Dependency (from/to) another project(s) | T-Shirt Size (XS, S, M, L, XL) | Project's Impact: Test Only (TO), Code (C) | Company Engagement | Notes | M4 Status |
---|---|---|---|---|---|---|---|---|---|
T-Shirt Size: Ballpark estimation for assessing the development/testing activities performed by the project team; not the integration team
- XS - <4 Man/Weeks;
- S - ~6 Man/Weeks;
- M - ~8 Man/Weeks;
- L - ~12 Man/Weeks;
- XL - > 12 Man/Weeks.