Discussion items
Duration | Agenda Item | Requested by | Notes / Links |
---|
START RECORDING |
| Reminder - next week meeting cancelled | Pamela Dragosh |
|
|
|
|
|
|
|
|
|
|
|
|
|
ATTENDEES
![](/download/attachments/92998003/Screen%20Shot%202020-11-18%20at%208.30.48%20AM.png?version=1&modificationDate=1605706730000&api=v2)
NOTES
- Next week's meeting cancelled due to upcoming Holiday week for US - most US based folks taking vacation.
- Discussion on CLAMP merger - where is it at? Still waiting to schedule meeting with arch committee
- questions regarding how does this affect Honolulu control loop testing? Folks do not have an answer.
- CLAMP maintenance for Honolulu does not impact DCAE or POLICY (except if the decision is approved and code needs to be moved. Resources will be impacted doing the work).
- Pamela Dragosh discussed plans for testing Drools PDP with shared distributed database. May result in features for Istanbul - TBD.
RECORDING