Milestones affected | N/A
|
Projects affected | N/A
|
Background description | The APPC project does not have a PTL and is not participating in the Jerma release and there are no resources for complying with these requirements. |
Schedule impact | N/A
|
Recovery plan | Find a new PTL and rejoin ONAP for the next release. |
Milestone schedule change | N/A
|
Risk | The security issues represented by these requirements will continue to be a risk. |