The plan be completed,I’m sorry to remind you that the final recovery plan and my response at the PTL meeting have changed a little bit
Here is the detail:
1、COMPLETION OF JAVA LANGUAGE UPDATE (v8 → v11)
Plan to implement in Instanbul ,the original plan was to be completed in RC0, But after evaluating the workload and considering that I did not create the OOM review with updated container image,so change to Instanbul.
2、CONTINUATION OF PACKAGES UPGRADES IN DIRECT DEPENDENCIES
Plan to implement in RC0, I am contacting Krzysztof Opasiak to solve the blocking problem metion in https://wiki.onap.org/x/nCDaB
Based on above feedback SECCOM recommends TSC to approve the exaception based on the MSB project commitmnet to upgrade to Java 11 in Instanbul release.
5 Comments
David McBride
Jinquan Ni - please complete recovery plan field.
Jinquan Ni
David McBride
The plan be completed,I’m sorry to remind you that the final recovery plan and my response at the PTL meeting have changed a little bit
Here is the detail:
1、COMPLETION OF JAVA LANGUAGE UPDATE (v8 → v11)
Plan to implement in Instanbul ,the original plan was to be completed in RC0, But after evaluating the workload and considering that I did not create the OOM review with updated container image,so change to Instanbul.
2、CONTINUATION OF PACKAGES UPGRADES IN DIRECT DEPENDENCIES
Plan to implement in RC0, I am contacting Krzysztof Opasiak to solve the blocking problem metion in https://wiki.onap.org/x/nCDaB
David McBride
Jinquan Ni please update the "milestone schedule change" field to indicate that you will complete the M3 requirements at RC0. Thanks.
Pawel Pawlak
Based on above feedback SECCOM recommends TSC to approve the exaception based on the MSB project commitmnet to upgrade to Java 11 in Instanbul release.
Jinquan Ni
2、CONTINUATION OF PACKAGES UPGRADES IN DIRECT DEPENDENCIES -----------------can be colsed(see: https://wiki.onap.org/x/nCDaB )