According to this Jira:
USECASEUI-545
-
Getting issue details...
STATUS
, Usecase UI team thought the deadline of committing the functional codes was RC0 because there was nothing about configuration to be updated, but OOM team thought it was too late because the deadline of merging functional codes should be M3, and also the new UUI NLP module had several problems, so we decided to postpone the merge date of UUI NLP, abandon the commit request of UUI NLP and ask the OOM team wether the rest part of UUI module could be merged into H release