DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass  Release Sign-Off Milestone.

Release Sign-Off Milestone overview is available in wiki.


Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)
Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre committed Product Backlog Stories been coded and marked as "Closed" in Jira?Yes

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh


Are all tasks associated with committed Product Backlog Stories been marked as "Closed" in Jira?Yes

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh


Provide the project features list under the form of a bulleted list.Yeshttps://onap.readthedocs.io/en/latest/submodules/multicloud/framework.git/docs/Release%20Notes.html#version-4-0-0-dublin-release

Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off

Yes

A list of stretch goals were planned but not delivered due to lack of resources, or not able to define clear functionality scope and use cases:

  • Add MultiCloud Normalization service for EA functional requirement
  • CDI support
  • Accelerator Management Support
  • Secure credential storage for AAI cloud region
  • Real-time capability as a cloud agnostic feature

Release ManagementHave all issues pertaining to FOSS been addressed?Yes

Have all findings from previous milestones been addressed?N/AProvide link to JIRA findings
DevelopmentAre all the Jenkins jobs successfully passed (verify + merge jobs)?Yes
https://jenkins.onap.org/view/Merge-Jobs/
Are all binaries available in Nexus Release repository?Yeshttps://nexus.onap.org/#nexus-search;quick~multicloud
Are all Docker images available In Nexus?Yeshttps://nexus3.onap.org/#browse/search=keyword%3Dmulticloud
Are the Java and Docker manifest updated with the same version as in Nexus Release repository?Yes

OOM to Tag Release + Version in Helm ChartYes

Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?


It should include at least 1 CSIT that will be run on


Lab-xxx-OOM-Daily Jenkins Job

Yeshttps://jenkins.onap.org/view/multicloud/Goal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs
Has the project code successfully passed the Daily Build process?Yeshttps://jenkins.onap.org/view/multicloud/Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the project passed the Integration Sanity TestsYes

Integration sanity tests in Dublin Release cover:

  • ONAP deployment
  • All components health check
  • VNF onboarding and service creation for vFW use case
  • Model distribution for vFW
  • vFW instantiation
  • vFW closed loop
  • vFW deletion

No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1

No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues

Has the project done the integration testing with related dependent projects?

Yes

Documentation

Has your team completed (reviewed, submitted and cherry picked) all documentation planned for the Dublin Release?

  1. Release Notes
  2. Project Documentation
  3. No remaining Documentation tickets
Yes

https://onap.readthedocs.io/en/latest/submodules/multicloud/framework.git/docs/Release%20Notes.html#version-4-0-0-dublin-release

https://onap.readthedocs.io/en/latest/submodules/multicloud/framework.git/docs/

JIRA Query

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC