Meeting Logistics

Meeting DayMeeting TimeConference Bridge
Fridays 6:00 AM to 7:00 AM (UTC-08:00) Pacific Time (US & Canada)https://zoom.us/j/454599760


ZOOM Conference Bridge

Join from PC, Mac, Linux, iOS or Android: https://zoom.us/j/454599760

Or iPhone one-tap (US Toll):  +14086380968,,454599760# or +16465588656,,454599760#

Or Telephone:

    Dial: +1 408 638 0968 (US Toll) or +1 646 558 8656 (US Toll)

    Meeting ID: 454 599 760

    International numbers available: https://zoom.us/zoomconference?m=viiAIbYha1FHOg4qZy9wY3LoQsy9Ut2P

Meeting Attendees

Meeting Agenda & Minutes

Agenda ItemsNotes

Logistics

Follow up on SDC meeting held on Monday. SDC will be pulling from VNF SDK.
M3 API Freeze Checklist
  • We are scheduled on TUE with ARC
  • Need to review integration tests with Integration team
  • Are there any issues or challenges for the team in meeting M3?
    • CSAR file is ready in the Marketplace.
    • The Package tools missed the M2 milestone. Should package alignment go into M3? Yes, we were given an extension to combine M2 and M3.

Sprint 2 progress

  • Modeling subteam (Andy Mayer)
    • VNFSDK-21 - Getting issue details... STATUS
    • VNFSDK-22 - Getting issue details... STATUS
    • VNFSDK-68 - Getting issue details... STATUS
    • New Mind Map and UML to be reviewed on the Modeling call today.
    • No blocking items for M3
  • Marketplace subteam (Weitao Gao)
    • VNFSDK-48 - Getting issue details... STATUS
    • working with SDC on this. Docker is built and everything has been moved into ONAP.
    • SDC can use image in the marketplace, which is optional. R1 is hardcoded.
    • Need to discuss this more with SDC. SDC says they don't want an external marketplace and are not committed to R1.
    • SDC using the VNF SDK marketplace is low priority for R1. This would mean they would need manual uploads in place of the marketplace.
    • Need to determine from SDC why they cannot implement this.
  • Validation Tools subteam (Murali Mohan Murthy Potham)
  • Package Tools subteam (Lianhao Lu)
    • VNFSDK-44 - Getting issue details... STATUS
    • Code is there and resolved the Jenkins issues.
    • We need to wait on SDC, 1 more week. Then we can start implementing.
  • Compliance
    • Not in scope for R1
  • Documentation
    • This will be needed for M4 for modeling and user guides.
Define Sprint 3

Subteams need to define their Sprint 3 features with estimates.

Will be two weeks starting from 8/21 to 9/1

Blockers/open issues

SDC Marketplace item.

ICE project is descoped from R1. We have no choice on this matter. Has this been reported to TSC? Will be done next week.