Release Schedule 

M0 (April 1) approved on March 18.  Other milestones TBD.

Approval TBD

Image AddedImage Removed


Change Log

DateEvent or UpdateMilestones Affected
Apr 28New proposal (r2) in response to feedback from original proposal.M1 - Sign Off
Mar 18Proposal presentation to TSC.  Requested approval of just the kickoff date of April 1.  Other milestones to be discussed at a later date.  TSC approved kickoff date ONLY.M0
Mar 11Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays.  Proposal not approved.ALL
Mar 10Second draft
  • Added a new milestone  before M3
  • Previous "M3" becomes M4
  • Added event in June
  • Moved Honolulu sign off to April 8
Mar 4Initial draft postedN/A

...