Development is delayed
JIRA story

Task

ONAP Component

Task DescriptionCommittersStatus

Notes


VNF CSAR defintion

SDC


  • Define import CSAR format
  • Define export CSAR format
Done


E2E service CSAR definitionSDC
  • Define E2E service CSAR format
Done

GUI WAN network design supportSDC
  • Define WAN underlay network using Underlay Network Service template
  • Define WAN overlay network using Overlay Network Service template
David ShadmiDoneIn R1, WAN design part is done through importing Network Service templates which define all parameters needed for WAN underlay and overlay networks.

GUI support on E2E service designSDC
  • Using SDC GUI to design VoLTE E2E service with vEPC, vIMS and WAN overlay and underlay networks
David ShadmiDoneWill add a link to the meeting recording which has a simple demo of VoLTE E2E service design

VoLTE service instantiation sequencing

SDC

  • SDC support of service instantiation sequencing by using Dependency construct
Done

SDC can support Dependency construct already


Support TOSCA VNFD importSDC
  • Support new node types used by VoLTE VNFD
RiskTime is very tight for SDC team because the design is finalized very recently

vEPC service designIntegration
  • Design network for vEPC
  • Define different design options
  • Work with VNF vendors to figure out the network design for vEPC



Need to discuss with integration team and come up with different design options


vIMS service designIntegration
  • Design network for vIMS
  • Define different design options
  • Work with VNF vendors to figure out the network design vIMS
Yang Xu


A&AI schema change to support ESRA&AI
  • Support ESR registration for VIM, SDN DC controller, SDN WAN controller, vendors' SVNFM and EMS
Done

A&AI schema change to support VFCVFC
  • Add new Network Service vertex in A&AI
In progress


Workflow design and implementationSO
  • Design a new SO NB interfaces for VoLTE E2E service LCM
  • Design and implement workflow for VoLTE E2E service
  • SO can use Dependency construct to implement service instantiation sequencing
In progress

Yang Xu Need to confirm with SO team they can use the dependency construct


DG design and implementation for WAN serviceSDNC
  • DG for WAN underlay network
  • DG for WAN overlay network
  • Integration with SO
High riskIntegration with the vendor's PE and DC Gateway is not tested yet


Holmes Correlation PolicyHolmes
  • Define correlation policy for VoLTE closed loop event. Different vendors will have different alarm code
RiskDevelopement is delayed


Closed loop configurationCLAMP
  • Support configuration of all closed loop policy related parameters
  • Distribute policy artifacts to DCAE, Holmes, and Policy
High RiskDevelopement is delayed, may not in MVP


Policy designPolicy
  • Support auto healing policy for VoLTE
  • Define auto healing policy in GUI

Pamela Dragosh

@integration

In progress

Integration team needs to talk to Policy team to see how to define the policy in GUI


Usecase UI developmentUsecase UI
  • Support all parameter input defined in VoLTE service template
  • Support VoLTE E2E service instantiation by clicking one button
  • Support alarm monitoring for ONAP and VoLTE service
High Risk

Development is delayed, and repo is still empty as of September 5, 2017