6/19/17 - APPC Project Kick-Off

...

Participants: Randa MaherAaron Hay, Patrick Brady, Skip Wonnell, Shubhada Vaze, Takamune Cho, Linda Horn, Veer Rajasekar, Tomasz Kaminski

Notes:

  • Review Beijing Milestones again (https://wiki.onap.org/display/DW/Release+Planning#ReleasePlanning-ONAPBeijingReleasePlanning)
    • 1/8 - Project Planning closure
    • M1 - 1/18 - M1 review
    • M2 - Functionality Freeze -  2/12
      • no new visible functionality is to be added to the current ONAP release
      • Each Project team has defined and documented their Functional Test Cases
      • A stable document describing the API is documented and available in wiki.
    • M3 - API Freeze - 3/8
      • Mark the end of API and Data Model change. API and Data Model are now Frozen
      • 50% of Functional Test Case are automated.
    • M4 - Code Freeze - 3/29  - 4/5/18 
      • Mark the end of the Features coding
      • 100% of Functional Test Case are automated
    • RC0 - Integration - 4/19
    • RC1
    • RC2
    • Release Delivery - 5/24 - Signoff
  • Review Current Dev resources
  • Review Scope
    • Remove references and use of openecomp and replace  with onap  APPC-13 - In progress
      • Action: Need to follow-up with Michael Lando on his concern….
    • Platform Maturity (or S3P)
      • Performance - cannot commit anything at this point; too many questions and ambigiuty on what needs to be done. Awaiting input from Benchmarking committee
      • Stability - 1 - 72 hours soak test on component level.
      • Resiliency - this item needs clarification - is 1 for local or geo-red manual failover? Regardless, we will align with CCSDK/SNDC since we get our ODL & DB dockers from them. We will work with SDNC team.
      • Security = 1  - CII Passing badge + 50% Test Coverag
      • Scalability -1 -  APPC uses ODL distribution from CCSDK project. Scaling is a function of ODL capabilities - adding nodes to an existing cluster or adding a new cluster
      • Manageability - 1- APPC supports EELF already.
      • Usability - 1

...

    • CDT Tool - an APP-C Design Tool enabling VNF owners to create templates and other artifacts for APP-C Configure command (used to apply a post-instantiation configuration) as well as other life cycle commands. Missing piece of functionality for Test Action
    • Documentation updates for Beijing
    • On-going requirements discussion during Beijing to fleshout requirement for vDNS scaling use case for Casablanca…  Pam/Brian/Paul/etc..

...

    • .

...

    • .

...

  • 1/8 - Project Planning closure
  • M1 - 1/18 - M1 review

Materials for M1:

- Release Planning Template:

• To be filled out by Jan 8. 10 days for review prior to TSC approval on Jan 18.

• Focus on scope and project dependencies

- Release Planning Checklist: To be filled out by Jan 17

  • M2 - Functionality Freeze -  2/12
    • no new visible functionality is to be added to the current ONAP release
    • Each Project team has defined and documented their Functional Test Cases
    • A stable document describing the API is documented and available in wiki.
  • M3 - API Freeze - 3/8
    • Mark the end of API and Data Model change. API and Data Model are now Frozen
    • 50% of Functional Test Case are automated.
  • M4 - Code Freeze - 3/29  - 4/5/18 
    • Mark the end of the Features coding
    • 100% of Functional Test Case are automated
  • RC0 - Integration - 4/19
  • RC1
  • RC2
  • Release Delivery - 5/24 - Signoff
  •  

...