New project proposal for Beijing are available here. These new projects will be reviewed by TSC during Santa Clara F2F the week of Dec 11-13 amd added to the list below as they are approved byTSC.
M1 Status
Conditions on projects:
- AAF: Pass with condition TSC need to agree on expending to CSM sub project scope.
- AAI: Pass with condition TSC need to agree on expending to Image Manager sub project scope.
- DCAE: Pass with condition on exception Cloudify manager.
- LOG: Pass with condition to review security guidelines and badges.
- OOM: Pass with Condition to Clarify Maturity scope.
- SO: Pass with Condition to reach 2 for Resiliency and Scalability at cpts Level (strectch ). Should be OK for 2 at Platform level.
...
| Project Name | Project Tech. Lead | M0 Kick-Off/Intention Submission
| M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery |
---|
1 | A & AI | | Oct 25, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
2 | Application Authorization Framework | | Nov 5, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
3 | APPC | | Nov 4, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
4 | CLAMP | | Oct 30, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
5 | Common Controller SDK | | Oct 13, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
6 | DCAE | | Nov 4, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
7 | DMaaP | | Nov 5, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
8 | Documentation | | Nov 4, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
9 | External API Framework | | Nov 7, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
10 | Holmes | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
11 | Integration | | Oct 25, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
12 | Logging Enhancements Project | | Oct 30, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
13 | Microservices Bus | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
14 | Modeling | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
15 | Multi VIM/Cloud | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
16 | MUSIC | | Jan 4, 2018 | Planning Checklist Pass |
|
|
|
|
|
|
|
17 | ONAP CLI | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
18 | ONAP Operations Manager | | Oct 26, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
19 | ONAP Optimization Framework | | Nov 6, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
20 | ONAP Usecase UI Project Proposal | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
21 | Policy Framework Project Proposal | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
22 | Portal Platform Project Proposal | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
23 | SDN-C | | Oct 13, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
24 | Service Design & Creation | | Oct 28, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
25 | Service Orchestrator | | Oct 25, 2017 | Planning Checklist Pass with condition |
|
|
|
|
|
|
|
26 | VF-C: Virtual Function Controller | | Oct 26, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
27 | VID project | | Oct 29, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
28 | VNF SDK | | Nov 20, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
29 | VNF Requirements | | Nov 6, 2017 | Planning Checklist Pass |
|
|
|
|
|
|
|
30 | VNF Validation (VVP) | | Oct 31, 2017 | Not reviewed. To be discussed at next TSC meeting |
|
|
|
|
|
|
|