6/19/17 - APPC Project Kick-Off

...

  • Testing
    • ConfigScaleOut (Ramya, Vidhya)
      • No progress on testing in WindRiver lab due to other blocking issues with APPC build.
    • CDT - did we get details from Amaresh?
    • Resiliency (Aaron)
    • Stability retest on Beijing (Scott)
      • Waiting on stable Beijing with Nitrogen to rerun the 72hour soak test
  • Upcoming milestone - RC0 on April 19.
    • APPC Beijing RC0 Checklist - Completed checklist and current disposition is: Not ready for RC0 yet,
      • Need to address failing jenkins jobs
      • Need to provide release version artifacts
      • Need to complete AAF story
      • Need to resolve issue with Request Handler bundle failure.
      • Failing CSIT we believe is related to LF performance issues. Requests are timing out. Hopefully with today's Nexus upgrade, CSIT tests will pass. Need to check tomorrow morning.

04/25/18 - APPC Project Weekly Minutes

ParticipantsRanda Maher; Recording:

Actions from last meeting:

  • Scott SeaboltAaron Hay to work together to pull together some lab diagrams for WindRiver lab setup for APPC usage (clustered vs non-clustered environments)
    • Update: 2-21-18: Information started to be populated here: APPC WindRiver Lab
    • Update: 3/21/18: Pending; however, note that all IP info is provided on wiki, diagram will be added later as time permits give other higher priority items.
    • Update: 4/25/18: CLOSED. APPC WindRiver Lab
  • Patrick Brady to provide a knowledge share on the changes that upgrade to Nitrogen brings to APPC once he is done with the ODL upgrade.
  • Randa Maher setup call to discuss testing in WindRiver APPC dev lab after we get Beijing successfully deployed.
    • Update: 3/28/18: Discussions started, but until we have a working Beijing environment
    • Update: 4/11/18: In-Progress
    • Update: 4/18/18: Team is still working through APPC w/Nitrogen stability; need to get past the issue with Request Handler not coming up. Until that's resolved, little testing can be done.
    • Update: 4/25/18: Still working through some blocking issues.
  • Ryan Young to investigate security vulnerabilty reported againt org.glassfish.grizzly, which is pulled in by CDP-PAL.
    • Update: 4/18/18: No update today, have more urgent items around AAF integration feature that still needs to be completed.
  • Takamune Chowill follow-up with Dan on SDNC project to see if he was able to successfully upgrade EELF. APPC has issues with version incompatibility with logback & sl4j and ODL.
  • Provide list of ODL plugins used by APPC (question raised by Andrej Zá?)

New Actions Items:

Agenda & Notes:

  • Blockers:
    • APPC Event Listener issue (APPC-859) blocking testing…
  • Pending items
    • AAF integration - documentation
      • Need final testing, and
      • Documentation on how to configure
      • Need to close out risk: Beijing Risks
    • Security items - what you got left Taka?
      • APPC-705  -httpclient-osgi : 4.3.3 -  can this be closed?
      • How about this one? org.apache.httpcomponents : httpclient : 4.5.2
      • APPC-706 - jackson-core : 2.3.2 - can this be closed?
      • APPC-841- org.glassfish.grizzly : grizzly-http : 2.3.28
    • Heat deployment to support CDT (Aaron)
      • Also - Is CDT going to be an issue with OOM deployment due to current constraint in Environments.ts?
  • Testing
    • CDT testing
    • ScaleOut testing
    • Resiliency tests
    • Generic_restart via multivim for regression - what are we missing?
  • Defects:
    • APPC-307 - can we close this one ? (Scott)
    • APPC-857 -  ccsdk-dgbuilder container failed - we need to fix this  (Patrick)
      • The issue appears to be that the paths for DG Builder have changed to ccsdk instead of sdnc.  We will update our APPC docker-compose.yml file to reflect the updated paths.
    • APPC-858 - merge change
  • Documentation:
    • APPC Properties documentation updates? (Vidhya and Ramya)
    • CDT UG updates
  • RC0 - still need to close out remaining items.
  • RC1 -

Integration

RC0

Avril 19, 2018

Release Candidate 0

RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases.

Project Team focused its effort on:

  1. supporting integration testing
  2. closing high priority defects
  3. supporting Documentation team


RC1

May 3, 2018

Release Candidate 1


RC2

May 17, 2018

Release Candidate 2

Sign-Off

Release Delivery

May 24, 2018

Beijing Release Sign-Off

https://wiki.onap.org/display/DW/Release+Planning#ReleasePlanning-CasablancaRelease>