Comment: Update status for CCVPN

...

Use CaseOwner

Projects or functional requirements Impacted

for Casablanca

Link(s) to High Level Design (HLD) /Low Level Design (LLD) (if any)Dependency (from/to) another project(s)T-Shirt Size (XS, S, M, L, XL)*Project's Impact: Test Only (TO), Code (C)Committed (C)/Partially Committed (P) or not (N) per Impacted projectsIf Partially or not Committed, then what are the gaps per impacted project (people/FTEs; HLD/LLD; etc)Company EngagementNotesM4 Status
vFWAT&THPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


vDNSAT&THPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


VoLTE

China Mobile

HPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


vCPEKang XiHPA


All: Test OnlyN/A - part of regression testsN/A - part of regression tests


CCVPN

SO,OOF,  SDNC,UUI, integration

Stretch goal:

SDC, DCAE, external API.

NOTE: No project should be code impacted by this use case.

Materials Lin Meng. Material Jianguo Zeng

All; Test

Code:

SO,OOF,  SDNC,UUI

Stretch goal:

SDC, DCAE, external API, CCSDK

SO:committed,

OOF:committed (Huawei resources as required).

UUI:committed

Integration: committed

SDNC: (Huawei resources as required).

Stretch goal:

DCAE :  Not committed(Huawei &CMCC plan to contribute)

SDC: Not committed

External API:(VDF & huawei plan to contribute)

CCSDK: (Huawei resources as required).

if projects not committed is just in strech goal, then we will dev based on exist features, may impact some usibiligy, but won't impact the final result.

DCAE : From discussion with Xin Miao (Huawei), this usecase requires new RESTCONF collector to be added into DCAE.This cannot be committed for R3 due to pending requirement clarification and architectural alignment besides resourcing constraint.

China Mobile, Vodafone

Contingent that Use Case owner are able to add resources on impacted projects and Integration agreement

Status
colourGreen
titleOn Track

POC Demo planned for ONS at Amsterdam

OSAM/PNF

SO, Portal, External API, APPC, DCAE

HPA

**NOTE: OSAM uses the PNF capability similar to 5G use case. No new development efforts were identified to support OSAM using PNF

VNFRQTS (include PNFs)

OSAM Material

All: Test Only

ATT, Turk Telecom, SwisscomContingent that Use Case owner are able to add resources on impacted projects and Integration agreement

Not M4 Gating

No Component development required for this usecase in Casablanca

Integration testing delayed due to resource contraint.

May need to defer to Dublin

...