- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- M3 Status
- M4 Status
- RC0 Status
- RC1 Status
- RC2 Status
Sign-off
Dublin Milestones Status
...
| |||||||||||
16 | MUSIC | Yes, per default | MUSIC Dublin M1 Deliverables for Planning Milestone Checklist | MUSIC Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: unit test coverage > 55% by M3. | |||||||
17 | ONAP CLI | Dec 3, 2018 | Dublin-M2-Checklist | ||||||||
18 | ONAP Operations Manager | Dec 3, 2018 | OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist | |||||||
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | |||||||
20 | ONAP Usecase UI | Yes, per default | Usecase-UI Beijing Release Planning Dublin Release M1 Deliverables for Planning Milestone Checklist | UUI Dublin M2 Functionality Freeze Milestone Checklist | |||||||
21 | Policy Framework | Dec 3, 2018 | Policy R4 Dublin M1 Release Planning Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template | Policy R4 Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template | |||||||
22 | Portal Platform | Nov 30, 2018 | Portal R4 M1 Release Planning (Dublin Release) Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release) | Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks | |||||||
23 | SDN-C | Yes, per default | SDNC : Dublin M2 : Functionality Freeze Milestone Checklist |
...
Condition: Unit test code coverage > 55% by M3 | ||||||
24 | Service Design & Creation | Dec 4, 2018 | SDC R4 Deliverables for Functionality Freeze Milestone Checklist |
...
Gerrit merge conflicts; non-root in process - need a plan Condition: unit test coverage > 55% by M3 | |||||||||||
25 | Service Orchestrator | Dec 2, 2018 | |||||||||
26 | VF-C: Virtual Function Controller | Dec 2, 2018 | VF-C Dublin: Deliverables for Functionality Freeze Milestone Checklist Template | ||||||||
27 | VID project | Dec 4, 2018 | VID R4 M2 Deliverables for Functionality Freeze Milestone Checklist | ||||||||
28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: (3x repos < 30%) Unit test coverage by M3 | |||||||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | ||||||||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template |