...
- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA 6 hour healthcheck (full 200G CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
General Status
- Dublin
- Stories in progress:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-959 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-766 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-767 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-551 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-665
- Stories to be formally verified before closure:
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-778
: For network resource only and should be split into Network Discovery and ND context builder.Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key SDNC-475 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-779 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-957 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key SDNC-637 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-958 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-404
- Stories closed since last meeting:
Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-763
- Bugs to enter:
- Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
- Bugs entered in last week:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-996 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-995 - Team focusing effort here. Will follow up with A&AI team for help
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-994 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-993 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-988 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-987 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-986
- Bugs in progress:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-852 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-975 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-976 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-967 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-916
- Bugs to be verified:
Jira showSummary true server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-807
(Verify in OOM fails, assigned back to design)Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-803 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-808 Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-981
- Bugs closed off since last meeting:
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-665 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-965 Jira server ONAP JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-966
- Stories in progress:
- Dublin
- Technical Discussion
- Consider demo schedules
- J. Ram Balasubramanian will forecast demos as development progresses
Data Dictionary & Network Discovery- Dec 20Done
- L2 Network data (Feb 21)
- video available
- Additional enhancement - March 21st
- additional resources and rules
- potentially other enhancements
- J. Ram Balasubramanian will forecast demos as development progresses
- Note we have discovered a number of discrepancies between the model definition in the wiki and the code. We are now raising bugs on specific issues found and will resolve as appropriate.
- Bugs raised; Issues fixed.
- Chesla to review mapping and provide feedback
- common model: https://wiki.onap.org/display/DW/POMBA+Common+Model
- This is out of date.
- common model mapping: https://wiki.onap.org/display/DW/Dublin+Common+Model+Mapping
- Reflects what has been implemented after some updates
- common model: https://wiki.onap.org/display/DW/POMBA+Common+Model
- Not all containers have health check enabled
- The gaps should be tracked. Action J.Ram.
- Consider demo schedules
- Validation Service and adding rules
- Action Yong to improve page or create a new one with better steps.
- Work has been done and Brian has seen
- Still looking for feedback from various folks and will update as appropriate.
- Issues raised in integration environment, we don't know how they have deployed. Need to figure out how to better work with integration team.
- This relates to the POD issues, where it was a problem with their manifest.
- We have no visibility of their current setup.
- PTLs will discuss with integration team to decide best path.
- Validation Service and adding rules
- There might be a late change to the PNF model
- We might get impacted
- Will they be backwards compatible? Ie, versioned
- Sharon to follow up Jimmy.
- Making the PTL Happy
- Casablanca
- Release notes being prepared.
- Still seems to be open.
- Data router version was upped. So, POMBA needed to update its version. This was integrated.
- There was a bug and the A&AI team fixed it. Integration team tested the fix, but perhaps did not test POMBA
J. Ram will quickly test.Michael O. did test already that the POD comes up and passes health check.J. Ram will confirm we did an audit.- Updated on
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key AAI-2090
- Updated on
- There was a bug and the A&AI team fixed it. Integration team tested the fix, but perhaps did not test POMBA
- Release notes being prepared.
- Dublin
- If you have concerns bring them to the TSC or the PTL meet - as I have a hard time convincing the TSC about issues without more developer voices
- Also for committer promotion - the template needs more data - 90/180/360 day commits, jira, discuss groups, wiki, reviewed commits, meeting attendance - as one of the committers for integration was rejected last week - any developer listed for committer promotion must attend the TSC 9-1030 to promote themselves and answer questions
- (+) 20190228: manifest confusion being addressed in TSC 2019-02-28 for
Jira server ONAP JIRA serverId 425b2b0a-557c-3c0c-b515-579789cceedb key LOG-966 - Should look at milestones and ensure we are in good shape.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Prudence is supporting Michael for this activity.
- we are at M2 not M1
- Logging Dublin M2 Deliverables for Functionality Freeze Milestone Checklist
https://wiki.onap.org/display/DW/Logging+Dublin+M1+Release+Planning
- Functionality freeze Feb 21/28
- Any new APIs are supposed have draft definition, but this doesn't really apply to us
- Michael has filled in the templates for POMBA. Should be good to go.
- API freeze is March 14th (or has this slipped?)
- Michael is starting to put together M3 checklist.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Casablanca