Dublin Milestones Status



Project NameProject Tech. LeadM0 Kick-Off/Intention Submission

M1

Planning

M2

Functionality freeze

M3

API Freeze

M4
Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery

1A & AI Dec 3, 2018

AAI R4 M1 Release Planning

AAI R4 M1 Deliverables for Planning Milestone Checklist

AAI R4 M2 Deliverables for Functionality Freeze Milestone Checklist

AAI R4 Deliverables for RC0 Milestone Checklist

AAI R4 Deliverables for RC1 Milestone Checklist

4 Docs jiras - recently updates


AAI R4 Deliverables for RC2 Milestone Checklist


Check on portal test results for AAI-2411

Docs in process


2Application Authorization FrameworkDec 3, 2018AAF R4 - M1 Release Plan
AAF R4 - M1 Milestone Checklist
AAF R4 - M2 Functionality Freeze Milestone Checklist
Condition: aaf-authz @55% by M3

AAF R4 -M3 Deliverables for API Freeze Milestone Checklist

Conditions: Obtain coverage goal by M4 - Failing Sonar coverage: aaf-authz

Need to update the checklist including Modeling Checklist item

Inprocess Gerrit: https://gerrit.onap.org/r/#/c/78520/

https://gerrit.onap.org/r/#/c/79224/

AAF R4 - M4 Deliverable for Code Freeze Milestone Checklist

AAF R4 (Dublin) - RC0 Milestone Checklist


TSC waiver for Dublin release sought: Sonar goal miss: aaf-authz


AAF R4 - RC1 Milestone Checklist


TSC waiver for Dublin release sought: Sonar goal miss: aaf-authz


AAF R4 - RC2 Milestone Checklist
3APPCYes, per default

APPC Dublin M1 Release Planning

APPC Dublin M1 Checklist

APPC Dublin M1 Security Checklist

APPC Dublin M2 Functionality Freeze Checklist

APPC Dublin M3 Deliverables for API Freeze Milestone Checklist Template


APPC Dubin M4 Code Freeze Milestone Checklist Template


APPC Dublin RC0 Milestone Checklist Template



APPC Dublin RC1 Milestone Checklist Template


2 high/highest - no update in last week

APPC Dublin RC2 Milestone Checklist


Open high

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution

maximumIssues20jqlQueryproject != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND issuetype = Bug AND Priority != Medium AND PRIOrity != Low AND Priority != Lowest AND fixVersion = "Dublin Release" AND status != Closed and status !=Delivered and project= "Application Controller" ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC

serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyAPPC-1613

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515

-579789cceedb4CLAMPYes, per defaultCLAMP R4 - M1 Release Planning
CLAMP R4 - M1 Deliverables for Planning Milestone ChecklistCLAMP R4 - M2 Functionality Freeze Milestone Checklist

CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist

Checklist complete - no swagger API doc

CLAMP R4 - M4 Deliverable for Code Freeze Milestone Checklist

CLAMP R4 - RC0 Milestone ChecklistCLAMP R4 - RC1 Milestone Checklist

CLAMP R4 - RC2 Milestone Checklist 

5Common Controller SDKYes, per default

CCSDK : Dublin: Release Planning

CCSDK : Dublin M1 : Deliverables for Planning Milestone

CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist

Condition: All repos unit test coverage > 55% by M3

CCSDK : Dublin M3 : API Freeze Milestone Checklist

Conditions: Unmet Sonar goal: passes as of 2019-04-09

CCSDK : Dublin M4 : Code Freeze Milestone Checklist

CCSDK : Dublin RC0 : Deliverables for RC0 Milestone Checklist

CCSDK : Dublin RC1 : Deliverables for RC1 Milestone Checklist

-579789cceedb
keyAPPC-1618


4CLAMPYes, per defaultCLAMP R4 - M1 Release Planning
CLAMP R4 - M1 Deliverables for Planning Milestone Checklist
CLAMP R4 - M2 Functionality Freeze Milestone Checklist

CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist


Checklist complete - no swagger API doc

CLAMP R4 - RC0 Milestone ChecklistCLAMP R4 - RC1 Milestone Checklist

CLAMP R4 - RC2 Milestone Checklist 



5Common Controller SDKYes, per default

CCSDK : Dublin: Release Planning

CCSDK : Dublin M1 : Deliverables for Planning Milestone

CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist

Condition: All repos unit test coverage > 55% by M3

CCSDK : Dublin M3 : API Freeze Milestone Checklist

Conditions: Unmet Sonar goal: passes as of 2019-04-09


CCSDK : Dublin RC1 : Deliverables for RC1 Milestone Checklist

Missing RC2

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyCCSDK-1324



6DCAEDec 5, 2018

DCAE R4 M1 Release Planning

DCAE R4 M1 Milestone Checklist

DCAE R4 M2 Functionality Freeze Milestone Checklist

DCAE R4 M3 Deliverables for API Freeze Milestone Checklist

Waiver requested, defer coverage goal (55%) for several items until M4:

dcaegen2-collectors-restconf

dcaegen2-collectors-snmptrap

dcaegen2-platform-inventory-api

DCAE R4 RC0 Milestone Checklist



DCAE R4 RC1 Milestone Checklist

1 Doc Jira Ticket

Missing RC2

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
key

CCSDK

DCAEGEN2-

1324

1540

6






7
DCAE

Vijay Venkatesh Kumar

Dec 5, 2018
DMaaPMandar SawantYes, per defaultDMaaP R4 -
DCAE R4
M1 Release Planning
DCAE
DMaaP R4 - M1 Milestone Checklist
DCAE
DMaaP R4 - M2 Functionality Freeze Milestone Checklist

DCAE R4 M3 Deliverables for API Freeze Milestone Checklist

Waiver requested, defer coverage goal (55%) for several items until M4:

dcaegen2-collectors-restconf

dcaegen2-collectors-snmptrap

dcaegen2-platform-inventory-api

DCAE R4 M4 Code Freeze Milestone Checklist

DCAE R4 RC0 Milestone Checklist

DCAE R4 RC1 Milestone Checklist

1 Doc Jira Ticket

DCAE R4 RC2 Milestone Checklist

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyDCAEGEN2-1540

Condition: All repos unit test coverage > 55% by M3, non-root post Dublin

DMaaP R4 - M3 API Freeze Milestone Checklist

Gerrit- Review

https://gerrit.onap.org/r/#/c/79574/

Modeling request for data model: "waiting on modeling team."

DMaap R4 - M4 Code Freeze Milestone Checklist

Swagger docs by RC2

DMaaP R4 - RC0 Milestone Checklist



DMaaP R4 - RC1 Milestone Checklist

DMaaP R4 - RC2 Milestone Checklist



8Documentation
7DMaaPMandar Sawant

Yes, per default
DMaaP R4 - M1 Release

Planning worksheet

DMaaP R4 - M1 Milestone Checklist

M1 Documentation Dublin Release

MS2 Deliverables for

DMaaP R4 - M2

Functionality Freeze Milestone Checklist

Condition: All repos unit test coverage > 55% by M3, non-root post Dublin

DMaaP R4 - M3 API Freeze Milestone Checklist

Gerrit- Review

https://gerrit.onap.org/r/#/c/79574/

Modeling request for data model: "waiting on modeling team."

DMaap R4 - M4 Code Freeze Milestone Checklist

Swagger docs by RC2

DMaaP R4 - RC0 Milestone Checklist

DMaaP R4 - RC1 Milestone Checklist

DMaaP R4 - RC2 Milestone Checklist

8DocumentationYes, per default

Planning worksheet

M1 Documentation Dublin Release

MS2 Deliverables for Functionality Freeze Milestone Checklist Template

Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables

Template

Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables

Moving to weekly documentation report... no checklist







9External API FrameworkDec 5, 2018Planning worksheet
M1 Checklist

[ExtAPI] Dublin M3 API Freeze Milestone Checklist


ExtAPI Dublin M4 Code Freeze Milestone Checklist

Project needs help getting signed certificates

ExtAPI Dublin RC0 Checklist



[ExtAPI] Dublin RC1 Checklist

2x Doc Jira Tickets

[ExtAPI] Dublin RC2 Checklist


Need to verify CSIT passing after NBI change


10HolmesDec 3, 2018

Holmes Release Planning for Dublin

Holmes Deliverables for Planning Milestone Checklist for Dublin

Holmes Deliverables for Functionality Freeze Milestone Checklist for Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28

Holmes Deliverables for API Freeze Milestone Checklist for Dublin


Holmes Deliverables for Code Freeze Milestone Checklist Template for Dublin


Moving some stories to next release due to lack of resource. No impact existing func.

Holmes Deliverables for RC0 Milestone for Dublin


Holmes Deliverables for RC1 Milestone for DublinHolmes Deliverables for RC2 Milestone for Dublin
11

Integration

Yes, per default

Integration Dublin M1 Deliverables for Planning Milestone Checklist

Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist
Provide status on the plan to close the blocker(s).

Integration Dublin M3 Deliverables for API Freeze Milestone Checklist

Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release.

Integration Dublin M4 Deliverable for Code Freeze Milestone ChecklistIntegration Dublin RC0 Milestone Checklist

12

Logging Enhancements Project

Including POMBA

Nov 16, 2018Logging Dublin M1 Release Planning
Logging Dublin Deliverables for Planning Milestone Checklist
Logging Dublin M2 Deliverables for Functionality Freeze Milestone Checklist

Logging

Moving to weekly documentation report... no checklist

9External API FrameworkDec 5, 2018Planning worksheet
M1 Checklist

[ExtAPI] Dublin M3 API Freeze Milestone Checklist

ExtAPI Dublin M4 Code Freeze Milestone Checklist

Project needs help getting signed certificates

ExtAPI Dublin RC0 Checklist

[ExtAPI] Dublin RC1 Checklist

2x Doc Jira Tickets

[ExtAPI] Dublin RC2 Checklist

Need to verify CSIT passing after NBI change

10HolmesDec 3, 2018

Holmes Release Planning for Dublin

Holmes Deliverables for Planning Milestone Checklist for Dublin

Holmes Deliverables for Functionality Freeze Milestone Checklist for Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28

Holmes Deliverables for API Freeze Milestone Checklist for Dublin

Holmes Deliverables for Code Freeze Milestone Checklist Template for Dublin

Moving some stories to next release due to lack of resource. No impact existing func.

Holmes Deliverables for RC0 Milestone for Dublin

Holmes Deliverables for RC1 Milestone for DublinHolmes Deliverables for RC2 Milestone for Dublin11

Integration

Yes, per default

Integration Dublin M1 Deliverables for Planning Milestone Checklist

Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist
Provide status on the plan to close the blocker(s).

Integration

Dublin M3 Deliverables for API Freeze Milestone Checklist

Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release.

Template

Checklist complete. No swagger API data

Logging

Integration

Dublin M4 Deliverable for Code Freeze Milestone Checklist Template

Integration

Logging Dublin RC0 Deliverables for RC0 Milestone Checklist

12

Logging Enhancements Project

Including POMBA

Nov 16, 2018



Logging Dublin RC1 Deliverables for RC1 Milestone Checklist



Logging Dublin RC2 Deliverables for RC2 Milestone Checklist

Documentation to be finalized


13Microservices BusNov 30, 2018

MSB Release Planning for Dublin

MSB

Logging Dublin M1 Release Planning
Logging Dublin

Deliverables for Planning Milestone Checklist

for Dublin

MSB Dubin
Logging Dublin M2
Deliverables for Functionality Freeze Milestone Checklist-M2
Logging Dublin M3

MSB Deliverables for API Freeze Milestone Checklist

Template

Checklist complete. No swagger API data

for Dublin


Logging Dublin M4 Deliverable
Template

MSB

Logging Dublin RC0

Deliverables for RC0 Milestone

Checklist

for Dublin

MSB
Logging Dublin RC1
Deliverables for RC1 Milestone
ChecklistLogging Dublin RC2
for DublinMSB Deliverables for RC2 Milestone
Checklist

Documentation to be finalized

for Dublin
14ModelingDec 3, 2018Modeling Dublin Planning
Modeling Dublin
13Microservices BusNov 30, 2018

MSB Release Planning for Dublin

MSB
Deliverables for Planning Milestone Checklist
for

Modeling Dublin

MSB Dubin

Deliverables for Functionality Freeze Milestone Checklist

-M2MSB

Condition: unit test coverage > 55% by M3

Modeling Dublin Deliverables for API Freeze Milestone Checklist

for Dublin

Condition: meet 55% coverage goal by M4

Sonar reporting warning: modeling-toscaparsers-javatoscachecker

MSB Deliverables
for


Modeling Dublin

MSB

Deliverables for RC0 Milestone

for

Checklist




Modeling Dublin
MSB
Deliverables for RC1 Milestone
for
ChecklistModeling Dublin
MSB
Deliverables for RC2 Milestone
for Dublin
Checklist
14Modeling

15Multi VIM/Cloud
Hui Deng

Dec 3, 2018
Modeling

MultiCloud Dublin Release Planning

Modeling Dublin

Deliverables for Planning Milestone Checklist

Modeling Dublin

Deliverables for Functionality Freeze Milestone Checklist

Condition16MUSICYes, per default

MUSIC Dublin Release Planning

MUSIC Dublin M1 Deliverables for Planning Milestone Checklist

MUSIC Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: unit test coverage > 55% by M3.

MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist

MUSIC
  1. Conditions: Get all remaining unit test code coverage > 55% by M3

Modeling Dublin Deliverables for API Freeze Milestone Checklist

Condition: meet 55% coverage goal by M4

Sonar reporting warning: modeling-toscaparsers-javatoscachecker

Modeling Dublin Deliverable for Code Freeze Milestone Checklist

Modeling Dublin Deliverables for RC0 Milestone Checklist

Modeling Dublin Deliverables for RC1 Milestone ChecklistModeling Dublin Deliverables for RC2 Milestone Checklist15Multi VIM/CloudDec 3, 2018

MultiCloud Dublin Release Planning

Deliverables for Planning Milestone Checklist

Deliverables for Functionality Freeze Milestone Checklist

  1. Conditions: Get all remaining unit test code coverage > 55% by M3
  2. Plan to design container(s) as non-root: M3 Dublin

MultiCloud R4 Deliverables for API Freeze Milestone Checklist

Conditional:

Need to add Modeling checklist item

Review gerrit (stale merges)

https://gerrit.onap.org/r/#/c/76324/

https://gerrit.onap.org/r/#/c/75851/

MultiCloud R4 Deliverable for Code Freeze Milestone Checklist

MultiCloud Deliverables for RC0 Milestone Checklist

TSC waiver for Dublin release sought: Sonar multicloud-azure below target

MultiCloud R4 Deliverables for RC1 Milestone Checklist

TSC waiver for Dublin release sought: Sonar multicloud-azure below target

MultiCloud R4 Deliverables for RC2 Milestone Checklist
  1. Plan to design container(s) as non-root: M3 Dublin

MultiCloud R4 Deliverables for API Freeze Milestone Checklist

Conditional:

Need to add Modeling checklist item

Review gerrit (stale merges)

https://gerrit.onap.org/r/#/c/76324/

https://gerrit.onap.org/r/#/c/75851/

MultiCloud R4 Deliverable for Code Freeze Milestone Checklist

MultiCloud Deliverables for RC0 Milestone Checklist



TSC waiver for Dublin release sought: Sonar multicloud-azure below target

MultiCloud R4 Deliverables for RC1 Milestone Checklist

TSC waiver for Dublin release sought: Sonar multicloud-azure below target

MultiCloud R4 Deliverables for RC2 Milestone Checklist

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyMULTICLOUD-660






16MUSICYes, per default

MUSIC Dublin Release Planning

MUSIC Dublin M1 Deliverables for Planning Milestone Checklist

MUSIC Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: unit test coverage > 55% by M3.

MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist




MUSIC Dublin M4 Code Freeze Milestone Checklist

MUSIC Dublin RC0 Milestone Checklist







https://wiki.onap.org/display/DW/MUSIC+Dublin+RC1+Milestone+Checklist

Missing RC2

Below Sonar goal: MUSIC


17ONAP CLIDec 3, 2018

Dublin-M1-CLI Deliverable

Dublin-M1-CLI Release planning

Dublin-M2-Checklist

Dublin-M3 checklist

Need to update the checklist including Modeling and additional Integration Checklist item

Dublin M4 Code Freeze Milestone Checklist
MUSIC

Dublin-RC0 Milestone Checklist

https://wiki.onap.org/display/DW/MUSIC+Dublin+RC1+Milestone+Checklist

Below Sonar goal: MUSIC17ONAP CLI


Dublin-RC1 Milestone Checklist

Old version in Dublin - 

Jira
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyCLI-168

Dublin-RC2 Milestone Checklist
18ONAP Operations Manager
user-67d6f

Dec 3, 2018

Dublin-M1-CLI Deliverable

Dublin-M1-CLI Release planning

Dublin-M2-Checklist

Dublin-M3 checklist

Need to update the checklist including Modeling and additional Integration Checklist item

OOM - Deliverables for Planning Milestone Checklist
OOM Dublin Release Planning Template

OOM Dublin - M2 Functionality Freeze Milestone Checklist


OOM Dublin - M3 API Freeze Milestone Checklist


Dublin M4

OOM Dublin - RC0 Milestone Deliverables Checklist


OOM Dublin - RC1 Milestone Deliverables Checklist

Old version in Dublin - 


OOM Dublin - RC2 Milestone Deliverables Checklist

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
key

CLI

OOM-

168Dublin-RC2 Milestone Checklist

1874

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyOOM-1851

18ONAP Operations ManagerDec 3, 2018OOM - Deliverables for Planning Milestone Checklist
OOM Dublin Release Planning Template

OOM Dublin - M2 Functionality Freeze Milestone Checklist

OOM Dublin - M3 API Freeze Milestone Checklist

OOM Dublin - M4 Deliverable for Code Freeze Milestone Checklist

OOM Dublin - RC0 Milestone Deliverables Checklist

I

OOM Dublin - RC1 Milestone Deliverables Checklist

OOM Dublin - RC2 Milestone Deliverables Checklist

Doc completion risk


19ONAP Optimization FrameworkDec 3, 2018OOF Dublin M1 Deliverables for Planning Milestone Checklist
OOF Dublin M1 Release Planning
OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3

OOF Dublin M3 Deliverables for API Freeze Milestone Checklist

Checklist complete.

Conditional: Complete unit test coverage goal by M4 for HAS and CMSO

OOM-CSIT BY M4

OOF Dublin RC0 Milestone Checklist

OOF Dublin RC2 Milestone Checklist

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyOPTFRA-513

Doc completion risk


20ONAP Usecase UIYes, per default

Usecase-UI Beijing Release Planning

Dublin Release M1 Deliverables for Planning Milestone Checklist

UUI Dublin M2 Functionality Freeze Milestone Checklist

Dublin Release M3 Deliverables for API Freeze Milestone Checklist


UUI Dublin M4 Code Freeze Milestone Checklist



Dublin Release Deliverables for RC0 Milestone Checklist


Dublin Release Deliverables for RC1 Milestone Checklist

2x Doc Jira Tickets

Dublin Release Deliverables for RC2 Milestone Checklist
21Policy FrameworkDec 3, 2018

Policy R4 Dublin M1 Release Planning

Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template

Policy R4 Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template

Policy R4 Dublin M3 Deliverables for API Freeze Milestone Checklist Template


Policy R4 Dublin M4 Deliverable for Code Freeze Milestone Checklist Template


Policy R4 Dublin RC0 Deliverables for RC0 Milestone Checklist Template


P-W testing

Policy R4 Dublin RC1 Deliverables for RC1 Milestone Checklist Template

1xDoc Jira Ticket

Policy R4 Dublin RC2 Deliverables for RC2 Milestone Checklist Template


Docs still under development

POLICY-1676


22Portal PlatformNov 30, 2018Portal R4 M1 Release Planning (Dublin Release)
Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release)
Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks

Portal R4 M3 Deliverables for API Freeze Milestone Checklist

Need to update the checklist including Integration & Modeling Checklist items



Portal R4 M4 for Code Freeze Milestone Checklist



Portal R4 RC0 Milestone Checklist



Portal R4 RC2 Dublin Milestone Checklist
23SDN-CYes, per default

SDNC : Dublin: Release Planning

SDNC : Dublin M1 : Deliverables for Planning Milestone

SDNC : Dublin M2 : Functionality Freeze Milestone Checklist

SDNC : Dublin RC0 : Deliverables for RC0 Milestone Checklist


Update certificate in RC1

SDNC : Dublin RC1 : Deliverables for RC1 Milestone Checklist

2 high in Submitted state

Certificate is updated

SDNC : Dublin RC2 : Deliverables for RC2 Milestone Checklist


Integration blocker: 

SDNC-756


24Service Design & CreationDec 4, 2018

SDC R4 Release Planning

SDC R4 Deliverables for Planning Milestone Checklist

SDC R4 Deliverables for Functionality Freeze Milestone Checklist

Condition: unit test coverage > 55% by M3

SDC R4 Deliverable for Code Freeze Milestone Checklist



SDC R4 Deliverables for RC0 Milestone Checklist


Sonar below goal: sdc master

SDC R4 Deliverables for RC1 Milestone Checklist

Waiver requested: Sonar below goal: sdc master



25Service OrchestratorDec 2, 2018

SO Dublin M1 Release Planning

SO Dublin M1 Checklist

Service Orchsttrator M2 Checklist

SO Dublin RC0: Deliverables for RC0 Milestone Checklist Template


SO Dublin RC1 Milestone Checklist Template

4 high/highest defects

SO Dublin - RC2 Milestone Checklist


1x high defect SO-1934


26VF-C: Virtual Function ControllerDec 2, 2018

VF-C Dublin M1 Release Planning

VF-C Dublin: Deliverables for Planning Milestone Checklist

VF-C Dublin: Deliverables for Functionality Freeze Milestone Checklist Template

VF-C Dublin: Deliverables for RC0 Milestone Checklist Template


DEPRECATED: Sonar warning (46%) on vfc-nfvo-driver-vnfm-svnfm-nokia-vnfmdriver

VF-C Dublin: Deliverables for RC1 Milestone Checklist Template

VF-C Dublin: Deliverables for RC2 Milestone Checklist Template


1x high defect VFC-1406

have delivered and wait for verification


27VID projectDec 4, 2018

VID R4 M1 Release Planning

VID R4 M1 Deliverables for Planning Milestone Checklist

VID R4 M2 Deliverables for Functionality Freeze Milestone Checklist

VID R4 M3 Deliverables for API Freeze Milestone Checklist

Missing swagger API info

In -process Integration blockers:

Jira
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyVID-429

Jira
serverONAP JIRA
serverId425b2b0a-557c-3c0c-b515-579789cceedb
keyVID-443


VID R4 M4 Deliverable for Code Freeze Milestone Checklist


VID R4 RC0 Milestone Checklist

VID R4 RC1 Milestone Checklist


RC0 images available. Build broken while converting to global-jjb


Missing RC2 & notified

Now available:

VID R4 RC2 Milestone Checklist


28VNF SDKDec 2, 2018

VNF SDK Dublin Release Planning (M1)

VNF SDK Deliverables for Planning Milestone Checklist Template(M1)

VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist

Conditional:

Unit test coverage by M3

VNF SDK Dublin API Freeze(M3)

Unit test coverage low: VNFSDK refrepo: 52.3% now is 55.3%




VNF SDK Dublin Code Freeze (M4)


Dublin VNFSDK RC0 Checklist - Release Candidate 0 MilestoneDublin VNFSDK RC1 Checklist - Release Candidate 1 MilestoneDublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone
29VNF RequirementsNov 16, 2018

Dublin Release Plan for VNFRQTS

M1 Deliverables for Planning Milestone Checklist Template

M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTSM3 Deliverables for API Freeze Milestone ChecklistM4 Deliverable for Code Freeze Milestone Checklist VNFRQTS

RC0 Milestone Checklist Template - VNFRQTS



RC1 Milestone - Checklist VNFRQTSRC2 Milestone checklist VNFRQTS
30VNF Validation (VVP)Nov 16, 2018

Dublin Release Plan for VVP

M1 Deliverables for Planning Milestone Checklist Template 

M2 Deliverables for Functionality Freeze Milestone Checklist Template


M3 Deliverables for API Freeze Milestone Checklist TemplateM4 Code Freeze Milestone Checklist Template for VVP

RC0 Milestone Checklist - VVP


RC1 Milestone Checklist -VVPRC2 Milestone checklist VVP