- M1 Status
- 1/24 - TSC 2019-01-24
- 16 out of 30 projects passed
- 16 out of 30 projects passed
- 1/31 -TSC 2019-01-31
- Project M1 Review. TSC Recommendations: Approved except Doc/Integration (additional information to be provided) - Project Status in Dublin Release
- M1 Scorecard Review: Dublin Release Requirements
- 1/24 - TSC 2019-01-24
- M2 Status -
- 2/14 - Please use the augmented checklist here: Deliverables for Functionality Freeze Milestone Checklist Template
- 2/28 - M2 Project Review. TSC Recommendations: Approved - Project Status in Dublin Release
- M3 Status
- 3/5 - Please use the augmented checklist here: Deliverables for API Freeze Milestone Checklist Template
- 3/14 - TSC Recommendations: Approved - https://wiki.onap.org/display/DW/TSC+2019-03-14
- M3 Project Review- Project Status in Dublin Release
- M3 Scorecard Review: Dublin Release Requirements
- M4 Status
- 4/4 - M4 milestone moved to 4/11 to avoid overlap with ONS
- 4/11- TSC 2019-04-11
- 9 out of 29 projects passed. Documentation is now tracked differently
- M4 scorecard not completed by the Owners
- 4/18 - TSC 2019-04-18
- Dublin M4 Milestone (Code Freeze) was passed on April 18th with gating exceptions that will be reviewed on April 25th 2019
- 4/26
- M4 Gating exceptions have been cleared
- RC0 Status
- RC1 Status
- RC2 Status
- Sign-off
Dublin Milestones Status
|
CLAMP R4 - M1 Deliverables for Planning Milestone Checklist
CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist
Checklist complete - no swagger API doc
CLAMP R4 - M4 Deliverable for Code Freeze Milestone Checklist
CLAMP R4 - RC2 Milestone Checklist
CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist
Condition: All repos unit test coverage > 55% by M3
CCSDK : Dublin M3 : API Freeze Milestone Checklist
Conditions: Unmet Sonar goal: passes as of 2019-04-09
CCSDK : Dublin M4 : Code Freeze Milestone Checklist
CCSDK : Dublin RC0 : Deliverables for RC0 Milestone Checklist
| |||||||||||||||||||||
4 | CLAMP | Yes, per default | CLAMP R4 - M1 Release Planning CLAMP R4 - M1 Deliverables for Planning Milestone Checklist | CLAMP R4 - M2 Functionality Freeze Milestone Checklist | CLAMP R4 - M3 Deliverables for API Freeze Milestone Checklist Checklist complete - no swagger API doc | CLAMP R4 - RC0 Milestone Checklist | CLAMP R4 - RC1 Milestone Checklist | CLAMP R4 - RC2 Milestone Checklist | |||||||||||||
5 | Common Controller SDK | Yes, per default | CCSDK : Dublin M2 : Functionality Freeze Milestone Checklist Condition: All repos unit test coverage > 55% by M3 | CCSDK : Dublin M3 : API Freeze Milestone Checklist Conditions: Unmet Sonar goal: passes as of 2019-04-09 | CCSDK : Dublin RC1 : Deliverables for RC1 Milestone Checklist | Missing RC2
| |||||||||||||||
6 | DCAE | Dec 5, 2018 | DCAE R4 M2 Functionality Freeze Milestone Checklist | DCAE R4 M3 Deliverables for API Freeze Milestone Checklist Waiver requested, defer coverage goal (55%) for several items until M4: | DCAE R4 RC0 Milestone Checklist | DCAE R4 RC1 Milestone Checklist 1 Doc Jira Ticket |
|
|
|
7 |
DMaaP | Mandar Sawant | Yes, per default | DMaaP R4 - |
M1 Release Planning |
DMaaP R4 - M1 Milestone Checklist |
DMaaP R4 - M2 Functionality Freeze Milestone Checklist |
DCAE R4 M3 Deliverables for API Freeze Milestone Checklist
Waiver requested, defer coverage goal (55%) for several items until M4:
DCAE R4 M4 Code Freeze Milestone Checklist
DCAE R4 RC0 Milestone Checklist
DCAE R4 RC1 Milestone Checklist
1 Doc Jira Ticket
DCAE R4 RC2 Milestone Checklist
Jira | ||||||||
---|---|---|---|---|---|---|---|---|
|
Condition: All repos unit test coverage > 55% by M3, non-root post Dublin | DMaaP R4 - M3 API Freeze Milestone Checklist Gerrit- Review https://gerrit.onap.org/r/#/c/79574/ Modeling request for data model: "waiting on modeling team." | DMaap R4 - M4 Code Freeze Milestone Checklist Swagger docs by RC2 | DMaaP R4 - RC0 Milestone Checklist | DMaaP R4 - RC1 Milestone Checklist | DMaaP R4 - RC2 Milestone Checklist | |
8 | Documentation |
Yes, per default |
DMaaP R4 - M3 API Freeze Milestone Checklist
Gerrit- Review
https://gerrit.onap.org/r/#/c/79574/
Modeling request for data model: "waiting on modeling team."
DMaap R4 - M4 Code Freeze Milestone Checklist
Swagger docs by RC2
DMaaP R4 - RC0 Milestone Checklist
DMaaP R4 - RC2 Milestone Checklist
MS2 Deliverables for Functionality Freeze Milestone Checklist Template
Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables
Condition: Followup to document the doc deliverables overtime so that rel_mgmt can support the deliverables | Moving to weekly documentation report... no checklist | ||||||||||
9 | External API Framework | Dec 5, 2018 | Planning worksheet M1 Checklist | [ExtAPI] Dublin M3 API Freeze Milestone Checklist | ExtAPI Dublin M4 Code Freeze Milestone Checklist Project needs help getting signed certificates | Need to verify CSIT passing after NBI change | |||||
10 | Holmes | Dec 3, 2018 | Holmes Release Planning for Dublin Holmes Deliverables for Planning Milestone Checklist for Dublin | Holmes Deliverables for Functionality Freeze Milestone Checklist for Dublin Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28 | Holmes Deliverables for API Freeze Milestone Checklist for Dublin | Holmes Deliverables for Code Freeze Milestone Checklist Template for Dublin Moving some stories to next release due to lack of resource. No impact existing func. | Holmes Deliverables for RC0 Milestone for Dublin | Holmes Deliverables for RC1 Milestone for Dublin | Holmes Deliverables for RC2 Milestone for Dublin | ||
11 | Yes, per default | Integration Dublin M1 Deliverables for Planning Milestone Checklist | Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist | Integration Dublin M3 Deliverables for API Freeze Milestone Checklist Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release. | Integration Dublin M4 Deliverable for Code Freeze Milestone Checklist | Integration Dublin RC0 Milestone Checklist | |||||
12 | Including POMBA | New PTL: Prudence Au | Nov 16, 2018 | Logging Dublin M1 Release Planning Logging Dublin Deliverables for Planning Milestone Checklist | Logging Dublin M2 Deliverables for Functionality Freeze Milestone Checklist |
Moving to weekly documentation report... no checklist
M1 Checklist
[ExtAPI] Dublin M3 API Freeze Milestone Checklist
ExtAPI Dublin M4 Code Freeze Milestone Checklist
Project needs help getting signed certificates
Need to verify CSIT passing after NBI change
Holmes Release Planning for Dublin
Holmes Deliverables for Planning Milestone Checklist for Dublin
Condition: holmes-common @55% by M3 (TBC) Non-root by 2019-02-28
Holmes Deliverables for API Freeze Milestone Checklist for Dublin
Holmes Deliverables for Code Freeze Milestone Checklist Template for Dublin
Moving some stories to next release due to lack of resource. No impact existing func.
Holmes Deliverables for RC0 Milestone for Dublin
Integration Dublin M1 Deliverables for Planning Milestone Checklist
Integration Dublin M2 Deliverables for Functionality Freeze Milestone Checklist
Provide status on the plan to close the blocker(s).
Need to understand if Integration has sufficient lab capacity for Dublin and a quick to follow maintenance release.
Checklist complete. No swagger API data |
Dublin M4 Deliverable for Code Freeze Milestone Checklist Template |
Including POMBA
New PTL: Prudence Au
Logging Dublin RC1 Deliverables for RC1 Milestone Checklist | Logging Dublin RC2 Deliverables for RC2 Milestone Checklist Documentation to be finalized | |||
13 | Microservices Bus | Nov 30, 2018 |
Logging Dublin
MSB Dubin |
Deliverables for Functionality Freeze Milestone Checklist-M2 |
Checklist complete. No swagger API data
MSB |
Deliverables for RC1 Milestone |
for Dublin | MSB Deliverables for RC2 Milestone |
Documentation to be finalized
for Dublin | ||||
14 | Modeling | Dec 3, 2018 | Modeling Dublin Planning Modeling Dublin |
MSB Release Planning for Dublin
MSBDeliverables for Planning Milestone Checklist |
Condition: unit test coverage > 55% by M3 | Modeling Dublin Deliverables for API Freeze Milestone Checklist |
Condition: meet 55% coverage goal by M4 Sonar reporting warning: modeling-toscaparsers-javatoscachecker |
Modeling Dublin |
Deliverables for RC1 Milestone |
Checklist | Modeling Dublin |
Deliverables for RC2 Milestone |
Checklist |
15 | Multi VIM/Cloud |
Dec 3, 2018 |
MUSIC Dublin M1 Deliverables for Planning Milestone Checklist
MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist
MUSIC
|
Modeling Dublin Deliverables for API Freeze Milestone Checklist
Condition: meet 55% coverage goal by M4
Sonar reporting warning: modeling-toscaparsers-javatoscachecker
Modeling Dublin Deliverable for Code Freeze Milestone Checklist
Modeling Dublin Deliverables for RC0 Milestone Checklist
Deliverables for Functionality Freeze Milestone Checklist
- Conditions: Get all remaining unit test code coverage > 55% by M3
- Plan to design container(s) as non-root: M3 Dublin
MultiCloud R4 Deliverables for API Freeze Milestone Checklist
Conditional:
Need to add Modeling checklist item
Review gerrit (stale merges)
MultiCloud R4 Deliverable for Code Freeze Milestone Checklist
MultiCloud Deliverables for RC0 Milestone Checklist
TSC waiver for Dublin release sought: Sonar multicloud-azure below target
MultiCloud R4 Deliverables for RC1 Milestone Checklist
TSC waiver for Dublin release sought: Sonar multicloud-azure below target
| MultiCloud R4 Deliverables for API Freeze Milestone Checklist Conditional: Need to add Modeling checklist item Review gerrit (stale merges) | MultiCloud R4 Deliverable for Code Freeze Milestone Checklist | MultiCloud Deliverables for RC0 Milestone Checklist TSC waiver for Dublin release sought: Sonar multicloud-azure below target | MultiCloud R4 Deliverables for RC1 Milestone Checklist TSC waiver for Dublin release sought: Sonar multicloud-azure below target | MultiCloud R4 Deliverables for RC2 Milestone Checklist
| |||||||||||
16 | MUSIC | Yes, per default | MUSIC Dublin M1 Deliverables for Planning Milestone Checklist | MUSIC Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template Condition: unit test coverage > 55% by M3. | MUSIC Dublin M3 Deliverables for API Freeze Milestone Checklist | MUSIC Dublin M4 Code Freeze Milestone Checklist | MUSIC Dublin RC0 Milestone Checklist | https://wiki.onap.org/display/DW/MUSIC+Dublin+RC1+Milestone+Checklist | Missing RC2 Below Sonar goal: MUSIC | |||||||
17 | ONAP CLI | Dec 3, 2018 | Dublin-M2-Checklist | Need to update the checklist including Modeling and additional Integration Checklist item |
Dublin M4 Code Freeze Milestone Checklist |
https://wiki.onap.org/display/DW/MUSIC+Dublin+RC1+Milestone+Checklist
Dublin-RC1 Milestone Checklist Old version in Dublin -
| Dublin-RC2 Milestone Checklist | ||||||||||
18 | ONAP Operations Manager |
Dec 3, 2018 |
Need to update the checklist including Modeling and additional Integration Checklist item
OOM - Deliverables for Planning Milestone Checklist OOM Dublin Release Planning Template | OOM Dublin - M2 Functionality Freeze Milestone Checklist | OOM Dublin - M3 API Freeze Milestone Checklist |
OOM Dublin - RC0 Milestone Deliverables Checklist |
OOM Dublin - RC2 Milestone Deliverables Checklist
|
|
|
OOM Dublin Release Planning Template
OOM Dublin - M2 Functionality Freeze Milestone Checklist
OOM Dublin - M3 API Freeze Milestone Checklist
OOM Dublin - M4 Deliverable for Code Freeze Milestone Checklist
OOM Dublin - RC0 Milestone Deliverables Checklist
I
OOM Dublin - RC1 Milestone Deliverables Checklist
OOM Dublin - RC2 Milestone Deliverables ChecklistDoc completion risk | |||||||||||||||||||||||||||
19 | ONAP Optimization Framework | Dec 3, 2018 | OOF Dublin M1 Deliverables for Planning Milestone Checklist OOF Dublin M1 Release Planning | OOF Dublin M2 Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | OOF Dublin M3 Deliverables for API Freeze Milestone Checklist Checklist complete. Conditional: Complete unit test coverage goal by M4 for HAS and CMSO OOM-CSIT BY M4 | OOF Dublin RC0 Milestone Checklist | OOF Dublin RC2 Milestone Checklist
Doc completion risk | ||||||||||||||||||||
20 | ONAP Usecase UI | Yes, per default | Usecase-UI Beijing Release Planning Dublin Release M1 Deliverables for Planning Milestone Checklist | UUI Dublin M2 Functionality Freeze Milestone Checklist | Dublin Release M3 Deliverables for API Freeze Milestone Checklist | UUI Dublin M4 Code Freeze Milestone Checklist | Dublin Release Deliverables for RC0 Milestone Checklist | Dublin Release Deliverables for RC1 Milestone Checklist 2x Doc Jira Tickets | Dublin Release Deliverables for RC2 Milestone Checklist | ||||||||||||||||||
21 | Policy Framework | Dec 3, 2018 | Policy R4 Dublin M1 Release Planning Policy R4 Dublin M1 Deliverables for Planning Milestone Checklist Template | Policy R4 Dublin M2 Deliverables for Functionality Freeze Milestone Checklist Template | Policy R4 Dublin M3 Deliverables for API Freeze Milestone Checklist Template | Policy R4 Dublin M4 Deliverable for Code Freeze Milestone Checklist Template | Policy R4 Dublin RC0 Deliverables for RC0 Milestone Checklist Template P-W testing | Policy R4 Dublin RC1 Deliverables for RC1 Milestone Checklist Template 1xDoc Jira Ticket | Policy R4 Dublin RC2 Deliverables for RC2 Milestone Checklist Template Docs still under development | ||||||||||||||||||
22 | Portal Platform | Nov 30, 2018 | Portal R4 M1 Release Planning (Dublin Release) Portal R4 M1 Deliverables for Planning Milestone Checklist (Dublin Release) | Portal R4 M2 Deliverables for Functionality Freeze Milestone Checklist Dependency on OOM for non-root testing; other dependencies articulated in the risks | Portal R4 M3 Deliverables for API Freeze Milestone Checklist Need to update the checklist including Integration & Modeling Checklist items | Portal R4 M4 for Code Freeze Milestone Checklist | Portal R4 RC0 Milestone Checklist | Portal R4 RC2 Dublin Milestone Checklist | |||||||||||||||||||
23 | SDN-C | Yes, per default | SDNC : Dublin M2 : Functionality Freeze Milestone Checklist | SDNC : Dublin RC0 : Deliverables for RC0 Milestone Checklist Update certificate in RC1 | SDNC : Dublin RC1 : Deliverables for RC1 Milestone Checklist 2 high in Submitted state Certificate is updated | SDNC : Dublin RC2 : Deliverables for RC2 Milestone Checklist Integration blocker: | |||||||||||||||||||||
24 | Service Design & Creation | Dec 4, 2018 | SDC R4 Deliverables for Functionality Freeze Milestone Checklist Condition: unit test coverage > 55% by M3 | SDC R4 Deliverables for API Freeze Milestone Checklist Condition: Meet 55% coverage goal by M4 Sonar (52+%) https://sonar.onap.org/dashboard?id=org.onap.sdc.sdc-distribution-client%3Asdc-main-distribution-client%3Amaster (49+%) https://sonar.onap.org/dashboard?id=org.openecomp.sdc%3Asdc-main%3Amaster Risks #20/21 | SDC R4 Deliverable for Code Freeze Milestone Checklist | SDC R4 Deliverables for RC0 Milestone Checklist Sonar below goal: sdc master | SDC R4 Deliverables for RC1 Milestone Checklist Waiver requested: Sonar below goal: sdc master | ||||||||||||||||||||
25 | Service Orchestrator | Dec 2, 2018 | SO Dublin RC0: Deliverables for RC0 Milestone Checklist Template | SO Dublin RC1 Milestone Checklist Template 4 high/highest defects | SO Dublin - RC2 Milestone Checklist 1x high defect SO-1934 | ||||||||||||||||||||||
26 | VF-C: Virtual Function Controller | Dec 2, 2018 | VF-C Dublin: Deliverables for Functionality Freeze Milestone Checklist Template | VF-C Dublin: Deliverables for API Freeze Milestone Checklist Template Checklist complete. Missing swagger API info | VF-C Dublin: Deliverables for RC0 Milestone Checklist Template DEPRECATED: Sonar warning (46%) on vfc-nfvo-driver-vnfm-svnfm-nokia-vnfmdriver | VF-C Dublin: Deliverables for RC1 Milestone Checklist Template | VF-C Dublin: Deliverables for RC2 Milestone Checklist Template 1x high defect VFC-1406 have delivered and wait for verification | ||||||||||||||||||||
27 | VID project | Dec 4, 2018 | VID R4 M2 Deliverables for Functionality Freeze Milestone Checklist | VID R4 M3 Deliverables for API Freeze Milestone Checklist Missing swagger API info In -process Integration blockers:
| VID R4 M4 Deliverable for Code Freeze Milestone Checklist | VID R4 RC0 Milestone Checklist | VID R4 RC1 Milestone Checklist RC0 images available. Build broken while converting to global-jjb | Missing RC2 & notified Now available: | |||||||||||||||||||
28 | VNF SDK | Dec 2, 2018 | VNF SDK Dublin Release Planning (M1) VNF SDK Deliverables for Planning Milestone Checklist Template(M1) | VNFSDK Dublin M2 Deliverables for Functionality Freeze Checklist Conditional: Unit test coverage by M3 |
| VNF SDK Dublin Code Freeze (M4) | Dublin VNFSDK RC0 Checklist - Release Candidate 0 Milestone | Dublin VNFSDK RC1 Checklist - Release Candidate 1 Milestone | Dublin VNFSDK RC2 Checklist - Release Candidate 2 Milestone | ||||||||||||||||||
29 | VNF Requirements | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist VNFRQTS | M3 Deliverables for API Freeze Milestone Checklist | M4 Deliverable for Code Freeze Milestone Checklist VNFRQTS | RC0 Milestone Checklist Template - VNFRQTS | RC1 Milestone - Checklist VNFRQTS | RC2 Milestone checklist VNFRQTS | |||||||||||||||||||
30 | VNF Validation (VVP) | Nov 16, 2018 | M2 Deliverables for Functionality Freeze Milestone Checklist Template | M3 Deliverables for API Freeze Milestone Checklist Template | M4 Code Freeze Milestone Checklist Template for VVP | RC1 Milestone Checklist -VVP | RC2 Milestone checklist VVP |