The scope of the Guilin Release of AAI will address CII Badging Security Program and Platform Maturity Requirements, as well the approved use cases.

Highest priority will be assigned to support security and platform maturity requirements.  As next highest priority, AAI will support the approved use cases.  Best-effort additional development will continue to support additional features not included in the approved use cases.

AAI R7 Guilin Release: TSC must have requirements

Requirements

AAI Use Case Impacts in R6TBD

Minimum Viable Product

  • A&AI Core: Resources - CRUD REST API endpoints for A&AI inventory resources
  • A&AI Core: Traversal - REST APIs for graph traversals.  Some APIs use the Gremlin Server
  • UI - An ONAP portal application used by operations for visualizing and searching
  • Data Router: Makes decisions about workloads to be dispatched to search and tabular microservces.  Includes logic to recognize and direct requests based on request archetypes.
  • Search - Enable complex searches for sub graphs and functions that need to perform well across deeply nested structures using Elasticsearch.  Used by the UI
  • Cacher - The Response Caching Microservice (Cacher) is built to deliver multiple mechanisms of making API calls and populating the responses into a JSON datastore. The datastore is an embedded mongodb datastore, that stores cached API responses, which are updated via DMAAP events or can be synced by timed tasks or calls to the force sync endpoint.
  • ESR - External System Registry component (provided community can deliver support, update vulnerable dependencies, and maintain the project)

...

List the functionalities that this release is committing to deliver by providing a link to JIRA Epics and Stories. In the JIRA Priority field, specify the priority (either High, Medium, Low). The priority will be used in case de-scoping is required. Don't assign High priority to all functionalities.

Epics

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject=AAI and issuetype in (epic) and status != "Closed"
serverId425b2b0a-557c-3c0c-b515-579789cceedb

Stories

Jira
serverONAP JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject=AAI and issuetype in (story)
serverId425b2b0a-557c-3c0c-b515-579789cceedb

TBD

Stories

TBD

Longer term roadmap

  • In future release, AAI looks toward additional simplification of visualization of the data model
  • Increased S3P, focusing on security and reducing turn around on 3rd party dependency vulnerabilities
  • Historical Data Tracking down to the attribute-level
  • Enhanced UI with animated state topology
  • AAI looks toward geo-redundant clusters of the Cassandra database
  • Tabular data views / aggregate views

...

Please fill out the centralized wiki page: Guilin Release Platform Maturity

AAI data is filled out


  • API Incoming Dependencies

List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the the release API Freeze freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

...

REST API(upload/query imagesREST API
API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)SOREST APIM3TBDAPPCREST APIM3TBDPOLICYREST APIM3TBDVIDREST APIM3TBDSDNCREST APIM3TBDHOLMESREST APIM3TBDVF-CREST APIM3TBDCLIREST APIM3TBDMultiVimREST APIM3TBDSDC)M3TBDExtAPIM3TBDUUIREST APIM3TBDOOFREST APIM3TBD





  • Third Party Products Dependencies

...

Provide a description of the testing activities (unit test, functional test, automation,...) that will be performed by the team within the scope of this release.

Describe the plan to integrate and test the release deliverables within the overall ONAP system.
Confirm that resources have been allocated to perform such activities.

AAI intends to move toward the SO model of gating for CSIT testing

AAI will participate in the Integration testing

AAI will do unit test within the WR AAI tenant space

AAI will contribute additional robot test tooling which does better regression testing

TBD

  • Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release.
List identified release gaps (if any), and its impact.

Gaps identifiedImpact
To fill outTo fill out
  • Known Defects and Issues

Please refer to Guilin Defect StatusTBD


  • Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Please update any risk on the centralized wiki page - Guilin Risks

  • Resources

Fill out the Resources Committed to the Release centralized page.TBD

  • Release Milestone

The milestones are defined at the Guilin Release LevelPlanning and all the supporting project agreed to comply with these dates.

...

  • Team contributions to the specific document related to he project (Config guide, installation guide...).
  • Team contributions to the overall Release Documentation and training asset
  • High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
  • Documentation includes items such as:
    • Installation instructions
    • Configuration instructions
    • Developer guide
    • End User guide
    • Admin guide
    • ...

...

titleNote

...

    • .

Other Information

  • Vendor Neutral

...