Project Name | Portal Platform |
---|---|
Target Release Name | R4 Dublin Release |
Project Lifecycle State | Incubation. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information |
Participating Company | AT&T, ChinaMobile, IBM, Amdocs |
Scope
What is this release trying to address?
...
- Locale/Internationalization language support – UsecaseUI project integration. (Chinamobile resources committed for this feature - Tao Shen)
- Reporting feature enhancement in portal/sdk (AT&T resources - Leimeng Shi )
- Angular 6 Upgrade of ONAP Portal and SDK with 1 or 2 new UI screens (IBM and AT&T resources partially committed - Deven Panchal and Saravanan Madheswaran)
- may impact partnering apps like Policy and VID
House Keeping (AT&T resources - Lorraine Welch, Amdocs resources)
- Maintain documentation for the architecture, APIs and release notes. (AT&T resources - Lorraine Welch)
- Improved logging - (Amdocs resource - Michael O'Brien )
Test Automation (IBM resources partially committed - Sireesh Chintamani )
...
Indicate at a high level the longer term roadmap. This is to put things into the big perspective.
Draft requirements Requirements for next Dublin release - road map
Release Deliverables
Indicate the outcome (Executable, Source Code, Library, API description, Tool, Documentation, Release Note...) of this release.
...
Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
Gaps identified | Impact |
---|---|
Security (No committed resources)
New features (No committed resources)
Address ONAP Platform Maturity Guidelines (No committed resources)
House Keeping (No committed resources)
| Updated in Dublin Risks Risk#3 - Security impact on Policy, VID apps that use portal/sdk regarding addressing NexusIQ security issues and AAF integration which is not committed by Portal team so far due to lack of resources; Risk#4 - Impacts Dublin platform maturity requirements (Footprint Optimization, Logging Capabilities). Also, OOM deployment is impacted if the DB scaling changes are not supported by Portal team; also the changes for simplification of etc/hosts entries impacts the OOM deployment which is not committed by Portal team so far due to lack of resources. |
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
Resources | Actively seeking community support. | Current resources are not enough to satisfy even the Highest Priority Epics |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
...