Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.

...

Risk identifiedMitigation PlanContingency Plan
documentaton tool chainprioritize tasks to resolve tool chaindefer to Beijing release

Resources

Fill out the Resources Committed to the Release centralized page.

Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

...

DateProjectDeliverable
July 21VNF Requirements seed contributions in proper formats and repos
July 28VNF Requirements

documentation tool chain generating:

  • VNF Guidelines
  • VNF Requirements
August 1VNF RequirementsSprint 1 defined
August 3VNF RequirementsM2: Test Cases Defined
August 15VNF RequirementsSprint 1 complete, Sprint 2 Defined
August 24VNF RequirementsM3:
August 29VNF RequirementsSprint 2 complete, Sprint 3 Defined
September 12VNF RequirementsSprint 3 complete, Sprint 4 Defined
September 14VNF RequirementsM4:(postponsed by TSC)
September 26VNF RequirementsSprint 4 complete, Sprint 5 Defined
September 28VNF RequirementsRC0M4
October 10VNF RequirementsSprint 5 complete, Sprint 6 Defined
October 12VNF RequirementsRC1RC0
October 24VNF RequirementsSprint 6 complete.
October 26VNF RequirementsRC2RC1
November 216VNF RequirementsRC2 / Signoff



Documentation, Training

...