Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
documentaton tool chain | prioritize tasks to resolve tool chain | defer to Beijing release |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
...
Date | Project | Deliverable |
---|---|---|
July 21 | VNF Requirements | seed contributions in proper formats and repos |
July 28 | VNF Requirements | documentation tool chain generating:
|
August 1 | VNF Requirements | Sprint 1 defined |
August 3 | VNF Requirements | M2: Test Cases Defined |
August 15 | VNF Requirements | Sprint 1 complete, Sprint 2 Defined |
August 24 | VNF Requirements | M3: |
August 29 | VNF Requirements | Sprint 2 complete, Sprint 3 Defined |
September 12 | VNF Requirements | Sprint 3 complete, Sprint 4 Defined |
September 14 | VNF Requirements | M4:(postponsed by TSC) |
September 26 | VNF Requirements | Sprint 4 complete, Sprint 5 Defined |
September 28 | VNF Requirements | RC0M4 |
October 10 | VNF Requirements | Sprint 5 complete, Sprint 6 Defined |
October 12 | VNF Requirements | RC1RC0 |
October 24 | VNF Requirements | Sprint 6 complete. |
October 26 | VNF Requirements | RC2RC1 |
November 216 | VNF Requirements | RC2 / Signoff |
Documentation, Training
...